7535 N BLOOMINGTON AVE 91504
Certificate Information: 7535 N BLOOMINGTON AVE 91504
- Application / Permit
- 23014-20000-00768
- Plan Check / Job No.
- B23VN02506
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Detached Garage Conversion and Addition to ADU per LAMC 12.22 A.33 (c) and (d)
- Permit Issued
- Issued on 8/29/2024
- Issuing Office
- Current Status
- CofO Issued on 9/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2023 | DAVID CASTILLO |
| Corrections Issued | 3/8/2023 | DAVID CASTILLO |
| Plan Check Approved | 7/27/2023 | CAROLEAN BASMA |
| Issued | 8/29/2024 | APPLICANT |
| CofO in Progress | 9/24/2025 | DAVID MATSON |
| Permit Finaled | 9/24/2025 | RUBEN SALAS |
| CofO Issued | 9/24/2025 | RUBEN SALAS |
| Permit Finaled | 9/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/27/2023 | CARLOS AGUILERA |
| Construction within easement | Cleared | 6/6/2023 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 7/24/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 7/24/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/27/2025 | Partial Approval | DAVID ANDERSON |
| Sewer | 1/27/2025 | Partial Approval | DAVID ANDERSON |
| Underground Mechanical | 1/27/2025 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 2/5/2025 | Corrections Issued | DAVID ANDERSON |
| Sewer | 2/5/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Sewer | 2/7/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 2/11/2025 | Approved | DAVID ANDERSON |
| Sewer | 2/27/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 4/8/2025 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 4/8/2025 | Corrections Issued | DAVID ANDERSON |
| Green Building Rough | 4/8/2025 | Approved | DAVID ANDERSON |
| HVAC-Rough | 4/8/2025 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 4/8/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 4/8/2025 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 4/10/2025 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 4/10/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 4/10/2025 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 4/10/2025 | Approved | DAVID ANDERSON |
| Shower Pan | 4/10/2025 | Approved | DAVID ANDERSON |
| Insulation | 4/15/2025 | Approved | DAVID ANDERSON |
| Drywall Nailing | 4/21/2025 | Approved | DAVID MATSON |
| Underground Mechanical | 5/7/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 7/10/2025 | Corrections Issued | DAVID ANDERSON |
| Underground Mechanical | 7/10/2025 | Approved | DAVID ANDERSON |
| Final | 7/29/2025 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 7/29/2025 | Approved | DAVID ANDERSON |
| MERV13>=Final | 7/29/2025 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 7/29/2025 | SGSOV Not Required | DAVID ANDERSON |
| Smoke Detectors | 7/29/2025 | Approved | DAVID ANDERSON |
| Final | 9/8/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 9/10/2025 | OK to Issue CofO | DAVID MATSON |