5149 N BEEMAN AVE 91607
Certificate Information: 5149 N BEEMAN AVE 91607
- Application / Permit
- 23014-20000-00764
- Plan Check / Job No.
- B23VN02493
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND 1ST AND 2ND FLOOR ADDITION TO CREATE (E) SINGLE FAMILY DWELLING TO CREATE (N) 51'-1" X 58'-5" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE AND PATIO COVER AND TRELLIS ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
- Permit Issued
- Issued on 6/26/2023
- Issuing Office
- Current Status
- CofO Issued on 10/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2023 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 3/16/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 3/17/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 3/21/2023 | APPLICANT |
| Applicant returned to address corrections | 6/5/2023 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 6/23/2023 | SEWADA ZADOORAN MILAGARDI |
| Issued | 6/26/2023 | APPLICANT |
| CofO in Progress | 10/2/2025 | OGANES TARAKHCHYAN |
| CofO Issued | 10/16/2025 | RUBEN SALAS |
| Permit Finaled | 10/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/17/2023 | CHRISTIAN PEARSON |
| ZI | Cleared | 4/17/2023 | CHRISTIAN PEARSON |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 4/18/2023 | ROMAN GUTIERREZ |
| Tract Map conditions | Cleared | 4/20/2023 | DANG NGUYEN |
| Permit | Cleared | 4/22/2023 | MARKOS PEREZ-BRAN |
| Trees in Parkway | Cleared | 5/17/2023 | ADALBERTO VERA |
| Construction near power lines | Cleared | 6/1/2023 | TORI CHEN |
| Construction within easement | Cleared | 6/1/2023 | TORI CHEN |
| Low Impact Development (LID) | Cleared | 6/1/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 6/2/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/27/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 5/29/2024 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 6/20/2024 | Approved | JOHN COLEMAN |
| Underground Mechanical | 8/8/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Underground Mechanical | 8/9/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 8/14/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | No Access for Inspection | SALVADOR MARTINEZ |
| Deputy Wood Construction | 10/31/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2024 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/21/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 11/21/2024 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 12/10/2024 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 12/10/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 12/10/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Wood Frame | 12/16/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Shower Pan | 12/19/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 12/24/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 12/24/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 12/31/2024 | Approved | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 1/9/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 1/9/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 1/9/2025 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 1/9/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 1/22/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 1/27/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 2/3/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 2/3/2025 | Approved | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 8/22/2025 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/22/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/22/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 8/28/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/28/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 9/5/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 9/5/2025 | Not Ready for Inspection | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 9/5/2025 | SGSOV Not Ready | WAYNE REGESTER |
| ELECTRICAL-Final | 9/23/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 9/23/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 9/23/2025 | Not Ready for Inspection | WAYNE REGESTER |
| HVAC-Final | 9/23/2025 | Not Ready for Inspection | WAYNE REGESTER |
| PLUMBING-Final | 9/23/2025 | Not Ready for Inspection | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 9/23/2025 | SGSOV Not Ready | WAYNE REGESTER |
| ELECTRICAL-Final | 9/25/2025 | Not Ready for Inspection | WAYNE REGESTER |
| HVAC-Final | 9/25/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 9/25/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 9/26/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 9/26/2025 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/26/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 10/1/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/1/2025 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 10/1/2025 | Approved | OGANES TARAKHCHYAN |