5149 N BEEMAN AVE 91607

Certificate Information: 5149 N BEEMAN AVE 91607

Application / Permit
23014-20000-00764
Plan Check / Job No.
B23VN02493
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND 1ST AND 2ND FLOOR ADDITION TO CREATE (E) SINGLE FAMILY DWELLING TO CREATE (N) 51'-1" X 58'-5" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE AND PATIO COVER AND TRELLIS ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 6/26/2023
Issuing Office
Current Status
CofO Issued on 10/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2023 APPLICANT
Assigned to Plan Check Engineer 3/9/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 3/16/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 3/17/2023 OMID HEDAYAT
Building Plans Picked Up 3/21/2023 APPLICANT
Applicant returned to address corrections 6/5/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 6/23/2023 SEWADA ZADOORAN MILAGARDI
Issued 6/26/2023 APPLICANT
CofO in Progress 10/2/2025 OGANES TARAKHCHYAN
CofO Issued 10/16/2025 RUBEN SALAS
Permit Finaled 10/16/2025 RUBEN SALAS

Permit Application Clearance Information

Specific Plan Cleared 4/17/2023 CHRISTIAN PEARSON
ZI Cleared 4/17/2023 CHRISTIAN PEARSON
Eng Process Fee Ord 176,300 Cleared 4/18/2023 ROMAN GUTIERREZ
Sewer availability Cleared 4/18/2023 ROMAN GUTIERREZ
Tract Map conditions Cleared 4/20/2023 DANG NGUYEN
Permit Cleared 4/22/2023 MARKOS PEREZ-BRAN
Trees in Parkway Cleared 5/17/2023 ADALBERTO VERA
Construction near power lines Cleared 6/1/2023 TORI CHEN
Construction within easement Cleared 6/1/2023 TORI CHEN
Low Impact Development (LID) Cleared 6/1/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 6/2/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/27/2024 Approved ROBERTO PALACIOS-LOPEZ
Pre-Inspection 5/29/2024 Approved MISAEL ESPARZA
Pre-Inspection 6/20/2024 Approved JOHN COLEMAN
Underground Mechanical 8/8/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 8/9/2024 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 8/14/2024 Conditional Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/19/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/20/2024 No Access for Inspection SALVADOR MARTINEZ
Deputy Wood Construction 10/31/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 11/21/2024 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 11/21/2024 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 12/10/2024 Approved GAREN HAYRAPETYAN
HVAC-Rough 12/10/2024 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 12/10/2024 Corrections Issued GAREN HAYRAPETYAN
Wood Frame 12/16/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Shower Pan 12/19/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 12/24/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 12/24/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 12/31/2024 Approved MICHAEL CORTEZ
BUILDING-Rough-Frame 1/9/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 1/9/2025 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 1/9/2025 Approved GAREN HAYRAPETYAN
Wood Frame 1/9/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 1/22/2025 Approved GAREN HAYRAPETYAN
Insulation 1/27/2025 Approved OGANES TARAKHCHYAN
Drywall Nailing 2/3/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 2/3/2025 Approved GAREN HAYRAPETYAN
Footing/Foundation/Slab 8/22/2025 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/22/2025 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 8/22/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 8/28/2025 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/28/2025 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 8/28/2025 Approved OGANES TARAKHCHYAN
Final 9/5/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 9/5/2025 Not Ready for Inspection WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 9/5/2025 SGSOV Not Ready WAYNE REGESTER
ELECTRICAL-Final 9/23/2025 Not Ready for Inspection WAYNE REGESTER
Final 9/23/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 9/23/2025 Not Ready for Inspection WAYNE REGESTER
HVAC-Final 9/23/2025 Not Ready for Inspection WAYNE REGESTER
PLUMBING-Final 9/23/2025 Not Ready for Inspection WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 9/23/2025 SGSOV Not Ready WAYNE REGESTER
ELECTRICAL-Final 9/25/2025 Not Ready for Inspection WAYNE REGESTER
HVAC-Final 9/25/2025 Approved WAYNE REGESTER
PLUMBING-Final 9/25/2025 Not Ready for Inspection WAYNE REGESTER
Final 9/26/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 9/26/2025 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/26/2025 SGSOV Not Ready OGANES TARAKHCHYAN
Final 10/1/2025 OK to Issue CofO OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/1/2025 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 10/1/2025 Approved OGANES TARAKHCHYAN