2275 S GUTHRIE CIR 90034
Certificate Information: 2275 S GUTHRIE CIR 90034
- Application / Permit
- 23014-20000-00749
- Plan Check / Job No.
- B23VN02420
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL TO (E)SFD, ENCLOSE (E) PATIO, AND ADDITION TO (E) DECK
- Permit Issued
- Issued on 10/25/2023
- Issuing Office
- Metro
- Current Status
- Issued on 10/25/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2023 | SERGIO MUNIZ |
| Corrections Issued | 3/5/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 3/22/2023 | APPLICANT |
| Applicant returned to address corrections | 4/26/2023 | CRISTINA SALAZAR |
| Plan Check Approved | 9/8/2023 | WEIJIAN HUANG |
| Issued | 10/25/2023 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/28/2023 | JASON NG |
| Grading Pre-Inspection | Cleared | 3/31/2023 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2023 | JASON NG |
| Roof/Waste drainage to street | Cleared | 8/23/2023 | JASON NG |
Contact Information
| Architect | Brettler-Weiner,, Linda Nanette; Lic. No.: C23458 | 1760 COURTNEY AVE. LOS ANGELES, CA 90046 |
| Contractor | M S Elite General Construction Inc; Lic. No.: 660454-B | 2040 CUMMINGS DRIVE LOS ANGELES, CA 90027 |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/30/2023 | Partial Approval | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 12/22/2023 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 12/22/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2025 | Corrections Issued | HERBERT GIRON |
| Special/Order Compliance | 11/4/2025 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2025 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 2/19/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 2/19/2026 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2026 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 2/24/2026 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/9/2026 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 3/9/2026 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 3/9/2026 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 3/17/2026 | Approved | WILBER ROSALES |
| Drywall Nailing | 3/25/2026 | Approved | DANIEL VERA |
| Special/Order Compliance | 3/25/2026 | Partial Inspection | HERBERT GIRON |