5530 N WILLOW CREST AVE 91601
Certificate Information: 5530 N WILLOW CREST AVE 91601
- Application / Permit
- 23014-20000-00744
- Plan Check / Job No.
- B23VN02394
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT (E) DETACHED GARAGE WITH ADDITION TO A DETACHED (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) AND NEW 2-CAR GARAGE ADDITION . ALL WORK PER ENGINEER DESIGN. "COMPLY WITH DEPARTMENT ORDER effective date 11/09/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 8/21/2023
- Issuing Office
- Current Status
- CofO Issued on 12/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 3/4/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 7/24/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 8/17/2023 | FARSHAD ALIMOHAMADI |
| Issued | 8/21/2023 | APPLICANT |
| CofO in Progress | 11/1/2024 | SCOTT SHUSTER |
| CofO Issued | 12/2/2024 | DAVID JAMES |
| Permit Finaled | 12/2/2024 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 5/18/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 5/26/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/9/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/29/2023 | Partial Inspection | SCOTT SHUSTER |
| Sewer | 9/13/2023 | Approved | SCOTT SHUSTER |
| Underground Mechanical | 9/13/2023 | Approved | SCOTT SHUSTER |
| Underground Mechanical | 9/29/2023 | Approved | SCOTT SHUSTER |
| Footing/Foundation/Slab | 11/13/2023 | Approved | SCOTT SHUSTER |
| Deputy Drilled-In Anchors | 11/14/2023 | Conditional Approval | SCOTT SHUSTER |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2024 | Approved | SCOTT SHUSTER |
| PLUMBING-Rough | 2/27/2024 | Approved | SCOTT SHUSTER |
| ELECTRICAL-Rough | 3/5/2024 | Partial Inspection | SCOTT SHUSTER |
| HVAC-Rough | 3/5/2024 | Partial Inspection | SCOTT SHUSTER |
| PLUMBING-Rough | 3/5/2024 | Approved | SCOTT SHUSTER |
| Deputy Drilled-In Anchors | 3/12/2024 | Conditional Approval | SCOTT SHUSTER |
| ELECTRICAL-Rough | 3/14/2024 | Approved | SCOTT SHUSTER |
| HVAC-Rough | 3/14/2024 | Approved | SCOTT SHUSTER |
| PLUMBING-Rough | 3/14/2024 | Approved | SCOTT SHUSTER |
| Wood Frame | 3/14/2024 | Partial Approval | SCOTT SHUSTER |
| Insulation | 3/15/2024 | Partial Approval | SCOTT SHUSTER |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Partial Inspection | SCOTT SHUSTER |
| Interior/Exterior Lathing | 3/18/2024 | Partial Inspection | SCOTT SHUSTER |
| Deputy Wood Construction | 3/20/2024 | Conditional Approval | SCOTT SHUSTER |
| Insulation | 3/22/2024 | Approved | SCOTT SHUSTER |
| Interior/Exterior Lathing | 3/22/2024 | Approved | SCOTT SHUSTER |
| Shower Pan | 3/22/2024 | Not Ready for Inspection | SCOTT SHUSTER |
| Wood Frame | 3/22/2024 | Approved | SCOTT SHUSTER |
| Drywall Nailing | 3/27/2024 | Approved | SCOTT SHUSTER |
| Shower Pan | 4/9/2024 | Approved | THOMAS WOODS |
| Interior/Exterior Lathing | 4/16/2024 | Approved | THOMAS WOODS |
| Final | 9/30/2024 | Partial Inspection | SCOTT SHUSTER |
| Green Building Final | 9/30/2024 | Approved | SCOTT SHUSTER |
| Green Building Rough | 9/30/2024 | Approved | SCOTT SHUSTER |
| SGSOV-Seismic Gas S/O Valve | 9/30/2024 | SGSOV Approved | SCOTT SHUSTER |
| Smoke Detectors | 9/30/2024 | Partial Approval | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 10/1/2024 | Approved | SCOTT SHUSTER |
| ELECTRICAL-Final | 10/25/2024 | Partial Inspection | SCOTT SHUSTER |
| Final | 10/25/2024 | Partial Inspection | SCOTT SHUSTER |
| HVAC-Final | 10/25/2024 | Approved | SCOTT SHUSTER |
| PLUMBING-Final | 10/25/2024 | Approved | SCOTT SHUSTER |
| Smoke Detectors | 10/25/2024 | Approved | SCOTT SHUSTER |
| Final | 10/31/2024 | Partial Approval | SCOTT SHUSTER |
| Final | 11/1/2024 | OK to Issue CofO | SCOTT SHUSTER |