6936 N JELLICO AVE 91406

Certificate Information: 6936 N JELLICO AVE 91406

Application / Permit
23014-20000-00723
Plan Check / Job No.
B23VN02336
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD TO & CONVERT (E) DET. GARAGE TO TO (N) ONE-STORY ACCESSORY DWELLING UNIT [PER LAMC 12.22 A.33 (c)-(d)] NEW BLDG DIM: 18' x 47'-4"
Permit Issued
Issued on 8/30/2024
Issuing Office
Current Status
CofO Issued on 11/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2023 APPLICANT
Assigned to Plan Check Engineer 3/2/2023 SEAN SHAHMIRI
Corrections Issued 3/6/2023 SEAN SHAHMIRI
Quality Review Completed 3/8/2023 OMID HEDAYAT
Building Plans Picked Up 3/9/2023 APPLICANT
Applicant returned to address corrections 4/10/2023 SEAN SHAHMIRI
Applicant returned to address corrections 5/1/2023 SEAN SHAHMIRI
Applicant returned to address corrections 5/8/2023 SEAN SHAHMIRI
Plan Check Approved 8/30/2024 SEAN SHAHMIRI
Issued 8/30/2024 APPLICANT
CofO in Progress 4/24/2025 JON MCHUGH
Permit Finaled 11/20/2025 JOHN JANSON
CofO Issued 11/20/2025 JOHN JANSON
Permit Finaled 11/20/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/14/2023 JOSE DUARTE-DIAZ
Construction near power lines Cleared 3/15/2023 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 3/20/2023 JOSE DUARTE-DIAZ
Sewer availability Cleared 3/20/2023 JOSE DUARTE-DIAZ
Hydrant and Access approval Cleared 3/25/2023 RUEL COLE
Low Impact Development (LID) Cleared 4/4/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 4/11/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
MORRIS JACKSON, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/25/2024 Partial Approval SEAN WIRCH
Excavation/Setback/Form/Re-Bar 10/2/2024 Approved SEAN WIRCH
Pre-Inspection 10/2/2024 Corrections Issued SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 11/27/2024 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Corrections Issued JON MCHUGH
HVAC-Rough 11/27/2024 Approved JON MCHUGH
BUILDING-Rough-Frame 12/9/2024 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Rough 12/9/2024 Approved JON MCHUGH
Gas Test 12/9/2024 Partial Approval JON MCHUGH
Green Building Rough 12/9/2024 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 12/9/2024 Approved JON MCHUGH
Verify Sprinkler Sign Off 12/9/2024 Approved JON MCHUGH
BUILDING-Rough-Frame 12/18/2024 Partial Inspection JOHN COLEMAN
Green Building Rough 12/18/2024 Partial Inspection JOHN COLEMAN
Interior/Exterior Lathing 12/18/2024 Approved JOHN COLEMAN
Insulation 12/31/2024 Corrections Issued JON MCHUGH
Insulation 1/8/2025 Approved JON MCHUGH
BUILDING-Rough-Frame 1/14/2025 Approved MORRIS JACKSON
Drywall Nailing 1/14/2025 Approved MORRIS JACKSON
Green Building Rough 1/14/2025 Approved MORRIS JACKSON
Shower Pan 1/14/2025 Approved MORRIS JACKSON
BUILDING-Rough-Frame 1/16/2025 Approved JON MCHUGH
Green Building Rough 1/16/2025 Approved JON MCHUGH
Interior/Exterior Lathing 1/16/2025 Approved JON MCHUGH
Gas Test 2/14/2025 Approved JON MCHUGH
ELECTRICAL-Final 4/10/2025 Corrections Issued ROBERT GOLD
HVAC-Final 4/10/2025 Corrections Issued ROBERT GOLD
PLUMBING-Final 4/10/2025 Approved ROBERT GOLD
ELECTRICAL-Final 4/18/2025 Approved JON MCHUGH
Final 4/18/2025 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 4/18/2025 Approved JON MCHUGH
Green Building Final 4/18/2025 Approved JON MCHUGH
HVAC-Final 4/18/2025 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 4/18/2025 SGSOV Not Ready JON MCHUGH
Smoke Detectors 4/18/2025 Approved JON MCHUGH
Final 4/23/2025 OK to Issue CofO JON MCHUGH
SGSOV-Seismic Gas S/O Valve 4/23/2025 SGSOV Approved JON MCHUGH