12019 N BEAUFAIT AVE 91326
Certificate Information: 12019 N BEAUFAIT AVE 91326
- Application / Permit
- 23014-20000-00716
- Plan Check / Job No.
- B23VN02300
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: ADDITION FOR A NEW RECREATIONAL ROOM TO THE REAR OF EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 5/19/2023
- Issuing Office
- Current Status
- CofO Issued on 9/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 3/2/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 4/28/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 5/16/2023 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 5/19/2023 | FARSHAD ALIMOHAMADI |
| Issued | 5/19/2023 | APPLICANT |
| CofO in Progress | 9/5/2023 | STEVEN BACK |
| Permit Finaled | 9/6/2023 | JOHN JANSON |
| CofO Issued | 9/6/2023 | JOHN JANSON |
| Permit Finaled | 9/6/2023 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/13/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2023 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 3/17/2023 | KIRK LINKLATER |
| Miscellaneous | Cleared | 3/29/2023 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/16/2023 | Partial Approval | STEVEN BACK |
| Pre-Inspection | 6/16/2023 | Partial Inspection | STEVEN BACK |
| Deputy Drilled-In Anchors | 6/21/2023 | Conditional Approval | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 6/22/2023 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 6/22/2023 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 7/18/2023 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 7/18/2023 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Approved | STEVEN BACK |
| Green Building Rough | 7/18/2023 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 7/18/2023 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 7/18/2023 | Approved | STEVEN BACK |
| Drywall Nailing | 7/28/2023 | Approved | STEVEN BACK |
| Green Building Rough | 7/28/2023 | Approved | STEVEN BACK |
| Insulation | 7/28/2023 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 7/28/2023 | Partial Approval | STEVEN BACK |
| Sewer | 7/28/2023 | Approved | STEVEN BACK |
| Shower Pan | 7/28/2023 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 8/1/2023 | Approved | JUSTIN HAWLEY |
| Final | 8/29/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 8/29/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 8/29/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 8/29/2023 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 9/5/2023 | Approved | STEVEN BACK |
| Final | 9/5/2023 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 9/5/2023 | Approved | STEVEN BACK |
| HVAC-Final | 9/5/2023 | Approved | STEVEN BACK |
| PLUMBING-Final | 9/5/2023 | Approved | STEVEN BACK |