12194 N HAVANA AVE 91342
Certificate Information: 12194 N HAVANA AVE 91342
- Application / Permit
- 23014-20000-00696
- Plan Check / Job No.
- B23VN02215
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-0" x 20'-0" DETACHED GARAGE WITH ADDITION OF 15'-0" x 17'-0" TO (N) DETACHED ACESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d) . WORK DONE PER WFPP.
- Permit Issued
- Issued on 4/3/2023
- Issuing Office
- Current Status
- CofO Issued on 12/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 3/2/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 4/3/2023 | MIROOSH KHACHATOORIAN |
| Issued | 4/3/2023 | APPLICANT |
| CofO in Progress | 10/28/2025 | JENNIFER RABUCHIN |
| CofO Issued | 12/2/2025 | RUBEN SALAS |
| Permit Finaled | 12/2/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2023 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 3/17/2023 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 3/17/2023 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/23/2023 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/7/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/7/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 8/14/2024 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/14/2024 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 8/20/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 8/21/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/21/2024 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/21/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 11/21/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/21/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/17/2025 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 1/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 1/17/2025 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/17/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/24/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 2/24/2025 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/15/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/15/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 7/15/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/15/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/15/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/15/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/28/2025 | Approved | JENNIFER RABUCHIN |
| Final | 7/28/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 7/28/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/28/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 7/28/2025 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/28/2025 | Approved | JENNIFER RABUCHIN |