6001 N CORBIN AVE 91356

Certificate Information: 6001 N CORBIN AVE 91356

Application / Permit
23014-20000-00677
Plan Check / Job No.
B23VN02123
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (N) FAMILY ROOM (IRR 15'-6" X 16') AT REAR & EXPAND (E) KITCHEN (35'-3" X 5') AT FRONT TO (E) 1-STORY SFD; INTERIOR REMODEL
Permit Issued
Issued on 9/5/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2023 APPLICANT
Assigned to Plan Check Engineer 2/23/2023 NILOOFAR MEHRAIN
Corrections Issued 2/28/2023 NILOOFAR MEHRAIN
Quality Review Completed 3/2/2023 STEVEN KIM
Building Plans Picked Up 3/3/2023 APPLICANT
Applicant returned to address corrections 8/10/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/22/2023 NILOOFAR MEHRAIN
Plan Check Approved 8/25/2023 NILOOFAR MEHRAIN
Issued 9/5/2023 APPLICANT
CofO in Progress 6/4/2024 MORRIS JACKSON
CofO in Progress 6/4/2024 MORRIS JACKSON
CofO in Progress 6/7/2024 MORRIS JACKSON
Permit Finaled 6/7/2024 JOHN JANSON
CofO Issued 6/7/2024 JOHN JANSON
Permit Finaled 6/7/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/16/2023 CARLOS AGUILERA
Sewer availability Cleared 3/16/2023 CARLOS AGUILERA
Low Impact Development (LID) Cleared 6/20/2023 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 6/21/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 8/10/2023 LAVEON RIDER

Contact Information

Contractor Owner-Builder       ,
Engineer Sabzehzar,, Habib; Lic. No.: C50442 8180 N PRICE AVE      FRESNO, CA 93720

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/5/2023 Conditional Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 10/10/2023 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Corrections Issued JON MCHUGH
Deputy Drilled-In Anchors 11/27/2023 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 12/1/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 12/5/2023 Corrections Issued JON MCHUGH
Rough-Elec/Plmb/HVAC 12/5/2023 Corrections Issued JON MCHUGH
Deputy Drilled-In Anchors 12/7/2023 Conditional Approval JON MCHUGH
BUILDING-Rough-Frame 12/8/2023 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 12/8/2023 Not Ready for Inspection JON MCHUGH
Green Building Rough 12/8/2023 Not Ready for Inspection JON MCHUGH
HVAC-Rough 12/8/2023 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 1/10/2024 Partial Approval JON MCHUGH
Footing/Foundation/Slab 1/10/2024 Corrections Issued JON MCHUGH
Excavation/Setback/Form/Re-Bar 1/16/2024 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 1/22/2024 Not Ready for Inspection JON MCHUGH
Footing/Foundation/Slab 1/29/2024 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 2/12/2024 Approved JON MCHUGH
Footing/Foundation/Slab 2/12/2024 Corrections Issued JON MCHUGH
Deputy Drilled-In Anchors 2/14/2024 Conditional Approval JON MCHUGH
Footing/Foundation/Slab 2/15/2024 Corrections Issued JON MCHUGH
Insulation 2/15/2024 Partial Approval JON MCHUGH
Drywall Nailing 2/20/2024 Partial Approval MORRIS JACKSON
Footing/Foundation/Slab 2/29/2024 Partial Approval JON MCHUGH
Footing/Foundation/Slab 4/3/2024 Approved JON MCHUGH
BUILDING-Rough-Frame 4/8/2024 Corrections Issued JON MCHUGH
Green Building Rough 4/8/2024 Not Ready for Inspection JON MCHUGH
BUILDING-Rough-Frame 4/11/2024 Partial Approval JON MCHUGH
ELECTRICAL-Rough 4/11/2024 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 4/16/2024 Approved JON MCHUGH
Interior/Exterior Lathing 4/19/2024 Partial Approval JON MCHUGH
BUILDING-Rough-Frame 4/30/2024 Approved JON MCHUGH
Final 4/30/2024 Corrections Issued JON MCHUGH
Green Building Final 4/30/2024 Not Ready for Inspection JON MCHUGH
Green Building Rough 4/30/2024 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 4/30/2024 SGSOV Not Ready JON MCHUGH
Smoke Detectors 4/30/2024 Corrections Issued JON MCHUGH
Final 5/31/2024 OK to Issue CofO MORRIS JACKSON
Green Building Final 5/31/2024 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 5/31/2024 SGSOV Approved MORRIS JACKSON
Smoke Detectors 5/31/2024 Approved MORRIS JACKSON
Final 6/4/2024 Corrections Issued MORRIS JACKSON