3633 1/2 S TRINITY ST 90011
Certificate Information: 3633 1/2 S TRINITY ST 90011
- Application / Permit
- 23014-20000-00673
- Plan Check / Job No.
- B23VN02104
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Convert (E) Garage to ADU and addition to ADU to build a 799 sf ADU. PER LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 1/10/2025
- Issuing Office
- Current Status
- Issued on 1/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2023 | ALFREDO JARA |
| Corrections Issued | 2/26/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 4/8/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 8/16/2023 | ALFREDO JARA |
| Plan Check Approved | 8/20/2023 | ALFREDO JARA |
| Issued | 1/10/2025 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/15/2023 | MICHAEL SOTO |
| Address approval | Cleared | 3/21/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2023 | JEANIE LAM |
| Sewer availability | Cleared | 3/22/2023 | JEANIE LAM |
| Construction near power lines | Cleared | 7/22/2023 | TINA MIRANDA |
| Low Impact Development (LID) | Cleared | 8/7/2023 | MEGAN PINKUS |
| Roof/Waste drainage to street | Cleared | 8/14/2023 | JEANIE LAM |
Contact Information
| Contractor | Tech Master Construction Inc; Lic. No.: 1054601-B | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/20/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Drilled-In Anchors | 3/21/2025 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/27/2025 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/16/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 4/16/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 4/18/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 4/18/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 4/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 4/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 4/22/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 4/28/2025 | Partial Approval | ANTHONY RAMOS |
| Interior/Exterior Lathing | 4/28/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 4/28/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 5/2/2025 | Approved | ANTHONY RAMOS |
| Sewer | 6/26/2025 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/4/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 8/13/2025 | Corrections Issued | WAYNE REGESTER |
| Final | 8/13/2025 | Corrections Issued | WAYNE REGESTER |
| HVAC-Final | 8/13/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 8/13/2025 | Corrections Issued | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 8/13/2025 | SGSOV Not Ready | WAYNE REGESTER |
| Service/Power Release | 8/13/2025 | Approved | WAYNE REGESTER |
| Smoke Detectors | 8/13/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 2/2/2026 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/2/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/2/2026 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/2/2026 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Final | 3/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 3/3/2026 | Approved | ALEJANDRO DE ARTOLA |