10211 N AMBOY AVE 91331
Certificate Information: 10211 N AMBOY AVE 91331
- Application / Permit
- 23014-20000-00666
- Plan Check / Job No.
- B23VN02098
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Addition to (E) 1-Story SFD per WFPP Standard Plans
- Permit Issued
- Issued on 4/7/2023
- Issuing Office
- Current Status
- Issued on 4/7/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2023 | DAVID CASTILLO |
| Corrections Issued | 2/26/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 3/22/2023 | DAVID CASTILLO |
| Plan Check Approved | 4/5/2023 | DAVID CASTILLO |
| Issued | 4/7/2023 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/6/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 3/8/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/12/2024 | Corrections Issued | RAUL VASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2024 | Approved | RAUL VASQUEZ |
| METHANE-Barrier | 4/25/2024 | Approved | RAUL VASQUEZ |
| METHANE-Subgrade | 4/25/2024 | Approved | RAUL VASQUEZ |
| Footing/Foundation/Slab | 4/26/2024 | Corrections Issued | RAUL VASQUEZ |
| Footing/Foundation/Slab | 5/31/2024 | Partial Approval | RAUL VASQUEZ |
| ELECTRICAL-Rough | 6/7/2024 | No Access for Inspection | MARIO CUEVAS |
| Footing/Foundation/Slab | 6/7/2024 | No Access for Inspection | MARIO CUEVAS |
| PLUMBING-Rough | 6/7/2024 | No Access for Inspection | MARIO CUEVAS |
| ELECTRICAL-Rough | 6/10/2024 | Approved | MARK VAN SLOOTEN |
| PLUMBING-Rough | 6/10/2024 | Corrections Issued | MARK VAN SLOOTEN |
| Pre-Inspection | 6/10/2024 | Corrections Issued | MARK VAN SLOOTEN |
| Footing/Foundation/Slab | 6/13/2024 | Approved | MARK VAN SLOOTEN |
| BUILDING-Rough-Frame | 6/17/2024 | Approved | MARK VAN SLOOTEN |
| Green Building Rough | 6/17/2024 | Approved | MARK VAN SLOOTEN |
| METHANE-Rough | 6/17/2024 | Approved | MARK VAN SLOOTEN |
| Interior/Exterior Lathing | 6/20/2024 | Approved | RAUL VASQUEZ |
| Drywall Nailing | 7/10/2024 | Approved | MARK VAN SLOOTEN |
| Final | 7/10/2024 | Conditional Approval | MARK VAN SLOOTEN |
| Green Building Final | 7/10/2024 | Approved | MARK VAN SLOOTEN |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Approved | MARK VAN SLOOTEN |
| Smoke Detectors | 7/10/2024 | Approved | MARK VAN SLOOTEN |