8333 N LURLINE AVE 91306
Certificate Information: 8333 N LURLINE AVE 91306
- Application / Permit
- 23014-20000-00655
- Plan Check / Job No.
- B23VN02071
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **ePlan** Rec. Room Addition at Rear of (E) 1-Story SFD w/Attached Garage "COMPLY WITH DEPARTMENT ORDER effective date 10/31/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 6/21/2023
- Issuing Office
- Current Status
- CofO Issued on 9/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2023 | DAVID CASTILLO |
| Corrections Issued | 2/28/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 3/18/2023 | DAVID CASTILLO |
| Plan Check Approved | 6/20/2023 | EDWIN ESPIN |
| Issued | 6/21/2023 | APPLICANT |
| CofO in Progress | 8/17/2023 | CHRIS CHRISTENSEN |
| Permit Finaled | 9/14/2023 | JOHN JANSON |
| CofO Issued | 9/14/2023 | JOHN JANSON |
| Permit Finaled | 9/14/2023 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/8/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2023 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 3/15/2023 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 3/15/2023 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 3/15/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 22634 SYLVAN ST WOODLAND HILLS, CA 91367 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/5/2023 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/5/2023 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/18/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 7/18/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/21/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 7/21/2023 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 7/21/2023 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 7/21/2023 | Approved | CHRIS CHRISTENSEN |
| Insulation | 8/2/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 8/2/2023 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 8/3/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 8/16/2023 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 8/16/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 8/16/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 8/16/2023 | Approved | CHRIS CHRISTENSEN |