5415 S 7TH AVE 90043
Certificate Information: 5415 S 7TH AVE 90043
- Application / Permit
- 23014-20000-00627
- Plan Check / Job No.
- B23VN01967
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 20' X 32'6" ADDITION TO REAR OF (E) SINGLE FAMILY DWELLING TO ADD MASTER BEDROOM, BATHROOM, LAUNDRY ROOM.
- Permit Issued
- Issued on 10/5/2023
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 3/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2023 | JESSE ARELLANO |
| Corrections Issued | 2/22/2023 | JESSE ARELLANO |
| Applicant returned to address corrections | 6/21/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 8/3/2023 | MADISON ODELL |
| Issued | 10/5/2023 | APPLICANT |
| CofO in Progress | 3/25/2026 | LUIS CASTRO |
| Permit Finaled | 3/30/2026 | DEROLD HAUFF |
| CofO Issued | 3/30/2026 | DEROLD HAUFF |
| Permit Finaled | 3/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Stormwater Pollution Mitigatn | Cleared | 6/27/2023 | TOMMY YIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2023 | JOSEPH RHYU |
| Roof/Waste drainage to street | Cleared | 10/3/2023 | JOSEPH RHYU |
| Sewer availability | Cleared | 10/3/2023 | JOSEPH RHYU |
Contact Information
| Contractor | Pure Passion Builders Inc; Lic. No.: 1102664-B | 4209 WEST 62ND STREET LOS ANGELES, CA 90043 |
| Engineer | Chaaya,, Danny Camille; Lic. No.: C45555 | P O BOX 46341 LOS ANGELES, CA 90046 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/1/2023 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 11/14/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/14/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/20/2023 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 11/27/2023 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/27/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 12/5/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2023 | Partial Approval | ANTHONY EGSON |
| Insulation | 12/6/2023 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2023 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/29/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 2/29/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 2/29/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 3/13/2024 | Partial Approval | ANTHONY EGSON |
| Wood Frame | 3/13/2024 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 3/18/2024 | Partial Approval | DAVID FEILER |
| Interior/Exterior Lathing | 4/9/2024 | Corrections Issued | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 4/9/2024 | Approved | ANTHONY EGSON |
| Shower Pan | 4/9/2024 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/12/2024 | Partial Inspection | JOSH MEISTER |
| Shower Pan | 4/12/2024 | Approved | JOSH MEISTER |
| Insulation | 4/18/2024 | Corrections Issued | CRAIG DAVIS |
| Drywall Nailing | 5/2/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/16/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 10/16/2024 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/16/2024 | SGSOV Not Ready | ANTHONY EGSON |
| Final | 10/23/2024 | Not Ready for Inspection | BARRY HACHE |
| Green Building Final | 10/23/2024 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 10/23/2024 | SGSOV Not Ready | BARRY HACHE |
| Smoke Detectors | 10/23/2024 | Not Ready for Inspection | BARRY HACHE |
| Final | 2/6/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 2/6/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 2/6/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 2/6/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 3/24/2026 | Approved | LUIS CASTRO |
| Final | 3/24/2026 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 3/24/2026 | Approved | LUIS CASTRO |
| PLUMBING-Final | 3/24/2026 | Approved | LUIS CASTRO |
| Final | 3/25/2026 | OK to Issue CofO | LUIS CASTRO |