5825 N JUMILLA AVE 91367
Certificate Information: 5825 N JUMILLA AVE 91367
- Application / Permit
- 23014-20000-00622
- Plan Check / Job No.
- B23VN01942
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 33'-9" x 43'-0" IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT W/ 21'-4" x 8'-0" OPEN TRELLIS PER LAMC 12.22 A.33(c) and (d). NFPA 13D FIRE SPRINKLERS PROVIDED
- Permit Issued
- Issued on 7/11/2023
- Issuing Office
- Current Status
- CofO Issued on 12/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 2/25/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 2/28/2023 | APPLICANT |
| Issued | 7/11/2023 | APPLICANT |
| CofO in Progress | 6/10/2024 | JON MCHUGH |
| No Progress | 1/13/2025 | JON MCHUGH |
| CofO in Progress | 1/13/2025 | JON MCHUGH |
| CofO in Progress | 9/22/2025 | JON MCHUGH |
| Permit Finaled | 12/12/2025 | JOHN JANSON |
| CofO Issued | 12/12/2025 | JOHN JANSON |
| Permit Finaled | 12/12/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/24/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/24/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 6/29/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/30/2023 | ROMAN GUTIERREZ |
| Hydrant and Access approval | Cleared | 7/11/2023 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/16/2023 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2023 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 9/12/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 9/14/2023 | Approved | JOHN KIDWELL |
| Shower Pan | 9/15/2023 | Approved | JOHN KIDWELL |
| HVAC-Rough | 9/18/2023 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2023 | Conditional Approval | JON MCHUGH |
| Underground Mechanical | 9/27/2023 | Approved | JON MCHUGH |
| Deputy Wood Construction | 10/2/2023 | Conditional Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 10/3/2023 | Approved | JON MCHUGH |
| Green Building Rough | 10/3/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 10/3/2023 | Partial Approval | JON MCHUGH |
| Verify Sprinkler Sign Off | 10/3/2023 | Approved | JON MCHUGH |
| Underground Mechanical | 10/5/2023 | Partial Approval | JEFFREY HARTLINE |
| Insulation | 10/12/2023 | Approved | MORRIS JACKSON |
| Drywall Nailing | 10/26/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 11/1/2023 | Corrections Issued | SEAN WIRCH |
| Interior/Exterior Lathing | 11/7/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 1/10/2024 | Corrections Issued | JON MCHUGH |
| HVAC-Final | 1/10/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 1/10/2024 | Corrections Issued | JON MCHUGH |
| Final | 1/17/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 1/17/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 1/17/2024 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 1/17/2024 | Not Required | JON MCHUGH |
| Smoke Detectors | 1/17/2024 | Approved | JON MCHUGH |
| Final | 6/10/2024 | OK to Issue CofO | JON MCHUGH |
| Special/Order Compliance | 1/13/2025 | Corrections Issued | JON MCHUGH |
| Final | 9/22/2025 | OK to Issue CofO | JON MCHUGH |