2325-2329 N TEVIOT ST 90039

Certificate Information: 2325-2329 N TEVIOT ST 90039

Application / Permit
23014-20000-00608
Plan Check / Job No.
B23VN01888
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT (E) ATTACHED 27'-2" x 21'-10" CARPORT AT LOWER LEVEL TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e).
Permit Issued
Issued on 10/10/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2023 APPLICANT
Assigned to Plan Check Engineer 2/21/2023 ARTIN ZARUKIAN
Corrections Issued 2/21/2023 ARTIN ZARUKIAN
Building Plans Picked Up 3/2/2023 APPLICANT
Plan Check Approved 7/12/2023 SARKIS HARABEDIAN
Issued 10/10/2023 APPLICANT
CofO in Progress 9/26/2024 HAMIK HARTOUNIAN
Permit Finaled 10/1/2024 RUBEN SALAS
CofO Issued 10/1/2024 RUBEN SALAS
Permit Finaled 10/1/2024 RUBEN SALAS

Permit Application Clearance Information

ZI Cleared 5/8/2023 SPENCER WEJROWSKI
Eng Process Fee Ord 176,300 Cleared 5/10/2023 TREVOR QUAN
Sewer availability Cleared 5/10/2023 TREVOR QUAN
Address approval Cleared 5/23/2023 TREVOR QUAN
Grading Pre-Inspection Cleared 7/12/2023 ARTIN ZARUKIAN

Contact Information

Contractor Doobek Inc; Lic. No.: 980653-B 5308 DERRY AVE   I-101, 102    AGOURA HILLS, CA 91301
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/23/2023 Partial Approval THOMAS LOGRASSO
Insulation 10/26/2023 Partial Approval THOMAS LOGRASSO
Deputy Wood Construction 10/31/2023 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 10/31/2023 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 11/9/2023 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 11/9/2023 Approved THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 11/21/2023 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 11/27/2023 Corrections Issued THOMAS LOGRASSO
Green Building Rough 11/27/2023 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 11/27/2023 Approved THOMAS LOGRASSO
Insulation 12/8/2023 Not Ready for Inspection THOMAS LOGRASSO
Drywall Nailing 1/8/2024 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 1/8/2024 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 2/23/2024 Approved THOMAS LOGRASSO
Green Building Rough 2/23/2024 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 2/23/2024 Approved THOMAS LOGRASSO
Drywall Nailing 5/10/2024 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 5/10/2024 Approved HAMIK HARTOUNIAN
Final 5/10/2024 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 5/10/2024 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Final 5/10/2024 Approved HAMIK HARTOUNIAN
PLUMBING-Final 5/10/2024 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 5/10/2024 Approved HAMIK HARTOUNIAN
Final 6/21/2024 Partial Inspection HAMIK HARTOUNIAN
Green Building Final 6/21/2024 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/21/2024 SGSOV Approved HAMIK HARTOUNIAN
Final 8/14/2024 Corrections Issued HAMIK HARTOUNIAN
Final 9/26/2024 OK to Issue CofO HAMIK HARTOUNIAN