2325-2329 N TEVIOT ST 90039
Certificate Information: 2325-2329 N TEVIOT ST 90039
- Application / Permit
- 23014-20000-00608
- Plan Check / Job No.
- B23VN01888
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (E) ATTACHED 27'-2" x 21'-10" CARPORT AT LOWER LEVEL TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e).
- Permit Issued
- Issued on 10/10/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 2/21/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 3/2/2023 | APPLICANT |
| Plan Check Approved | 7/12/2023 | SARKIS HARABEDIAN |
| Issued | 10/10/2023 | APPLICANT |
| CofO in Progress | 9/26/2024 | HAMIK HARTOUNIAN |
| Permit Finaled | 10/1/2024 | RUBEN SALAS |
| CofO Issued | 10/1/2024 | RUBEN SALAS |
| Permit Finaled | 10/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 5/8/2023 | SPENCER WEJROWSKI |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 5/10/2023 | TREVOR QUAN |
| Address approval | Cleared | 5/23/2023 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 7/12/2023 | ARTIN ZARUKIAN |
Contact Information
| Contractor | Doobek Inc; Lic. No.: 980653-B | 5308 DERRY AVE I-101, 102 AGOURA HILLS, CA 91301 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/23/2023 | Partial Approval | THOMAS LOGRASSO |
| Insulation | 10/26/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 10/31/2023 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 11/9/2023 | Approved | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 11/21/2023 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/27/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 11/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 11/27/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 12/8/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Drywall Nailing | 1/8/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 1/8/2024 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/23/2024 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 2/23/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 2/23/2024 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 5/10/2024 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 5/10/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 5/10/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 5/10/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 5/10/2024 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 5/10/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/10/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 6/21/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 6/21/2024 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 6/21/2024 | SGSOV Approved | HAMIK HARTOUNIAN |
| Final | 8/14/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 9/26/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |