12554 W MIRANDA ST 91607
Certificate Information: 12554 W MIRANDA ST 91607
- Application / Permit
- 23014-20000-00575
- Plan Check / Job No.
- B23VN01762
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: REMODEL AND 1150 SF ADDITION TO SFD AND INTERIOR REMODEL
- Permit Issued
- Issued on 4/5/2023
- Issuing Office
- Current Status
- CofO Issued on 1/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | CRYSTEL MAALOUF |
| Corrections Issued | 3/13/2023 | CRYSTEL MAALOUF |
| Quality Review Completed | 3/14/2023 | FARUK SEZER |
| Plan Check Approved | 4/5/2023 | CRYSTEL MAALOUF |
| Issued | 4/5/2023 | APPLICANT |
| CofO in Progress | 1/9/2024 | JUAN VALENZUELA |
| Permit Finaled | 1/9/2024 | RUBEN SALAS |
| CofO Issued | 1/9/2024 | RUBEN SALAS |
| Permit Finaled | 1/9/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 3/20/2023 | COLIN LOREDO |
| Low Impact Development (LID) | Cleared | 4/3/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 4/5/2023 | COLIN LOREDO |
Contact Information
| Contractor | Heskel Developments; Lic. No.: 1081833-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/1/2023 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 5/1/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/12/2023 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 5/12/2023 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2023 | Partial Approval | KIRK SANDERS |
| Deputy Wood Construction | 6/8/2023 | Conditional Approval | MICHAEL SMITH |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 6/23/2023 | Corrections Issued | KIRK SANDERS |
| Shower Pan | 6/23/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 6/28/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 6/28/2023 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 6/28/2023 | Partial Approval | KIRK SANDERS |
| Shower Pan | 6/28/2023 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 6/29/2023 | Approved | KIRK SANDERS |
| Shower Pan | 6/29/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 6/30/2023 | Approved | KIRK SANDERS |
| Insulation | 7/6/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 7/6/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 7/12/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 7/12/2023 | Approved | KIRK SANDERS |
| Sewer | 8/4/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 8/4/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 9/13/2023 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 9/29/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 10/2/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 10/2/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 10/13/2023 | Corrections Issued | KIRK SANDERS |
| Gas Test | 10/13/2023 | Approved | KIRK SANDERS |
| PLUMBING-Final | 10/13/2023 | Approved | KIRK SANDERS |
| Final | 10/19/2023 | Conditional Approval | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/19/2023 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 10/19/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 12/11/2023 | Approved | JUAN VALENZUELA |
| Final | 12/11/2023 | Partial Inspection | JUAN VALENZUELA |
| Gas Test | 12/11/2023 | Approved | JUAN VALENZUELA |
| Service/Power Release | 1/9/2024 | Approved | JUAN VALENZUELA |