7833 S HENEFER AVE 90045

Certificate Information: 7833 S HENEFER AVE 90045

Application / Permit
23014-20000-00567
Plan Check / Job No.
B23VN01732
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF (E) GARAGE/REC. ROOM AND ADDITION OF 2ND STORY TO ADU PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 11/6/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 JESSE ARELLANO
Corrections Issued 2/17/2023 JESSE ARELLANO
Building Plans Picked Up 2/22/2023 APPLICANT
Applicant returned to address corrections 4/10/2023 MADISON ODELL
Applicant returned to address corrections 5/3/2023 RAMA DABADGE
Applicant returned to address corrections 9/15/2023 ANGELICA DAVE
Issued 11/6/2023 APPLICANT
CofO in Progress 5/31/2024 TEMISTOCLES CAAL
Permit Finaled 6/4/2024 DANIEL ORRANTE
CofO Issued 6/4/2024 DANIEL ORRANTE
Permit Finaled 6/4/2024 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/27/2023 ROBERT PINA
Address approval Cleared 3/2/2023 JASON NG
Specific Plan Cleared 3/2/2023 SPENCER WEJROWSKI
Eng Process Fee Ord 176,300 Cleared 3/6/2023 JASON NG
Sewer availability Cleared 3/6/2023 JASON NG
Construction near power lines Cleared 4/29/2023 RIDWAN HARDY

Contact Information

Contractor F S Design & Construction Inc; Lic. No.: 727272-B 20520 OXNARD ST      WOODLAND, CA 91367
Engineer Segovia,, Felipe; Lic. No.: C41102 2622 DORSET DR      TORRANCE, CA 90503

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/8/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 11/14/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 11/21/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 1/19/2024 Not Ready for Inspection TEMISTOCLES CAAL
Rough-Elec/Plmb/HVAC 1/19/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 1/23/2024 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 1/23/2024 Approved TEMISTOCLES CAAL
Green Building Rough 1/23/2024 Approved TEMISTOCLES CAAL
Insulation 1/29/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 1/29/2024 Approved BEN MOLSTAD
Shower Pan 1/29/2024 Approved BEN MOLSTAD
Drywall Nailing 2/2/2024 Approved HERBERT GIRON
Final 2/2/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 5/8/2024 Corrections Issued TEMISTOCLES CAAL
Final 5/8/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 5/8/2024 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 5/8/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 5/8/2024 Corrections Issued TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 5/8/2024 SGSOV Approved TEMISTOCLES CAAL
Smoke Detectors 5/8/2024 Approved TEMISTOCLES CAAL
Final 5/15/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Final 5/15/2024 Corrections Issued TEMISTOCLES CAAL
Final 5/30/2024 OK to Issue CofO TEMISTOCLES CAAL
Gas Test 5/30/2024 Approved TEMISTOCLES CAAL
Green Building Final 5/30/2024 Approved TEMISTOCLES CAAL