7833 S HENEFER AVE 90045
Certificate Information: 7833 S HENEFER AVE 90045
- Application / Permit
- 23014-20000-00567
- Plan Check / Job No.
- B23VN01732
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) GARAGE/REC. ROOM AND ADDITION OF 2ND STORY TO ADU PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 11/6/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | JESSE ARELLANO |
| Corrections Issued | 2/17/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 2/22/2023 | APPLICANT |
| Applicant returned to address corrections | 4/10/2023 | MADISON ODELL |
| Applicant returned to address corrections | 5/3/2023 | RAMA DABADGE |
| Applicant returned to address corrections | 9/15/2023 | ANGELICA DAVE |
| Issued | 11/6/2023 | APPLICANT |
| CofO in Progress | 5/31/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 6/4/2024 | DANIEL ORRANTE |
| CofO Issued | 6/4/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/4/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/27/2023 | ROBERT PINA |
| Address approval | Cleared | 3/2/2023 | JASON NG |
| Specific Plan | Cleared | 3/2/2023 | SPENCER WEJROWSKI |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2023 | JASON NG |
| Sewer availability | Cleared | 3/6/2023 | JASON NG |
| Construction near power lines | Cleared | 4/29/2023 | RIDWAN HARDY |
Contact Information
| Contractor | F S Design & Construction Inc; Lic. No.: 727272-B | 20520 OXNARD ST WOODLAND, CA 91367 |
| Engineer | Segovia,, Felipe; Lic. No.: C41102 | 2622 DORSET DR TORRANCE, CA 90503 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/8/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 11/14/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2023 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2023 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Rough-Elec/Plmb/HVAC | 1/19/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 1/23/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 1/23/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 1/29/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 1/29/2024 | Approved | BEN MOLSTAD |
| Shower Pan | 1/29/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 2/2/2024 | Approved | HERBERT GIRON |
| Final | 2/2/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 5/8/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 5/8/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 5/8/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 5/8/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 5/8/2024 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 5/8/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 5/8/2024 | Approved | TEMISTOCLES CAAL |
| Final | 5/15/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 5/15/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 5/30/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| Gas Test | 5/30/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Final | 5/30/2024 | Approved | TEMISTOCLES CAAL |