PROPOSED 21'-6" x 46'-0" 1-STORY ADDITION TO THE (E) SINGLE FAMILY DWELLING FOR A NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). ALL WORK PER WFPP. """The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy."""""
Permit Issued
Issued on 3/8/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 JESSE ARELLANO
Corrections Issued 2/18/2023 JESSE ARELLANO
Building Plans Picked Up 2/22/2023 APPLICANT
Plan Check Approved 3/8/2023 SARKIS HARABEDIAN
Issued 3/8/2023 APPLICANT
CofO in Progress 8/22/2024 VINCENT HANLEY
CofO Issued 8/31/2024 DANIEL ORRANTE
Permit Finaled 8/31/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/25/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/28/2023 CARLOS AGUILERA
Sewer availability Cleared 2/28/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/6/2023 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/6/2023 Partial Approval CHRISTOPHER DELLEFIELD
Underground Mechanical 6/6/2023 Partial Approval CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 6/9/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 6/15/2023 Not Ready for Inspection RAUL OLAGI
Excavation/Setback/Form/Re-Bar 6/16/2023 Approved WILLIAM WREN
Excavation/Setback/Form/Re-Bar 6/16/2023 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Partial Approval MISAEL ESPARZA
Green Building Rough 7/17/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 7/17/2023 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 7/17/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 7/17/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 9/26/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 9/26/2023 Approved GREGG CUMMINGS
Green Building Rough 9/26/2023 Approved GREGG CUMMINGS
HVAC-Rough 9/26/2023 Corrections Issued GREGG CUMMINGS
Interior/Exterior Lathing 9/26/2023 Not Ready for Inspection GREGG CUMMINGS
MERV13>=Rough 9/26/2023 Approved GREGG CUMMINGS
HVAC-Rough 9/29/2023 Corrections Issued DAVID MATSON
Interior/Exterior Lathing 9/29/2023 Partial Approval DAVID MATSON
HVAC-Rough 10/4/2023 Corrections Issued CHRISTOPHER ROJAS
Wood Frame 10/4/2023 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/11/2023 Approved GREGG CUMMINGS
HVAC-Rough 10/11/2023 Corrections Issued GREGG CUMMINGS
HVAC-Rough 10/17/2023 Approved MISAEL ESPARZA
Insulation 10/17/2023 Partial Approval MISAEL ESPARZA
Drywall Nailing 10/23/2023 Approved GREGG CUMMINGS
Insulation 10/23/2023 Approved GREGG CUMMINGS
Shower Pan 11/15/2023 Approved GREGG CUMMINGS
Final 12/22/2023 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 12/22/2023 Approved GREGG CUMMINGS
Green Building Final 12/22/2023 Approved GREGG CUMMINGS
MERV13>=Final 12/22/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 12/22/2023 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 12/22/2023 Approved GREGG CUMMINGS
ELECTRICAL-Final 6/5/2024 Approved VINCENT HANLEY
Final 6/5/2024 Corrections Issued VINCENT HANLEY
HVAC-Final 6/5/2024 Approved VINCENT HANLEY
PLUMBING-Final 6/5/2024 Approved VINCENT HANLEY
Final 8/5/2024 Corrections Issued VINCENT HANLEY
Final 8/22/2024 OK to Issue CofO VINCENT HANLEY