11301-11301 1/2 N MONOGRAM AVE 91344

Certificate Information: 11301-11301 1/2 N MONOGRAM AVE 91344

Application / Permit
23014-20000-00537
Plan Check / Job No.
B23VN01610
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 20'-9" x 21'-2" (439 SF) OF (E) SINGLE FAMILY DWELLING INTO NEW JUNIOR ACCESSORY DWELLING UNIT [PER CA Govt. Code 65852.2(e)(1)(A) and 65852.22], AND REMOVE NON-BEARING WALLS OF (E) KITCHEN; AND ADD NEW 9' x 25'-3" ONE-CAR CARPORT TO (E) SINGLE FAMILY DWELLING UNIT; ALL WORK PER WFPP & LA CITY STANDARD DETAILS
Permit Issued
Issued on 4/18/2023
Issuing Office
Current Status
CofO Issued on 10/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2023 APPLICANT
Assigned to Plan Check Engineer 2/23/2023 SEAN SHAHMIRI
Corrections Issued 3/2/2023 SEAN SHAHMIRI
Quality Review Completed 3/3/2023 OMID HEDAYAT
Building Plans Picked Up 3/6/2023 APPLICANT
Applicant returned to address corrections 4/18/2023 SEAN SHAHMIRI
Plan Check Approved 4/18/2023 SEAN SHAHMIRI
Issued 4/18/2023 APPLICANT
CofO in Progress 10/23/2024 ROBERT GOLD
CofO Issued 10/23/2024 DANIEL ORRANTE
Permit Finaled 10/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/29/2023 MICHAEL TEMPLE
Low Impact Development (LID) Cleared 4/5/2023 ROGELIO CORTES
Eng Process Fee Ord 176,300 Cleared 4/7/2023 ROMAN GUTIERREZ
Permit Cleared 4/7/2023 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 4/7/2023 ROMAN GUTIERREZ
Address approval Cleared 4/18/2023 CARLOS AGUILERA
Sewer availability Cleared 4/18/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 5/11/2023 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 5/25/2023 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 6/1/2023 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 6/1/2023 Partial Approval JAVIER RAMOS JR
Wood Frame 6/1/2023 Partial Inspection JAVIER RAMOS JR
Drywall Nailing 7/5/2023 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 7/5/2023 Approved JAVIER RAMOS JR
Wood Frame 7/5/2023 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 11/6/2023 Not Ready for Inspection JAVIER RAMOS JR
Final 11/6/2023 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 11/6/2023 Approved JAVIER RAMOS JR
MERV13>=Final 11/6/2023 Approved JAVIER RAMOS JR
MERV13>=Rough 11/6/2023 Approved JAVIER RAMOS JR
Smoke Detectors 11/6/2023 Not Ready for Inspection JAVIER RAMOS JR
Pre-Inspection 12/18/2023 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 2/12/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 2/12/2024 Approved JAVIER RAMOS JR
Final 2/12/2024 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 2/12/2024 Approved JAVIER RAMOS JR
Final 9/19/2024 OK to Issue CofO JAVIER RAMOS JR