10220 N ELDORA AVE 91040

Certificate Information: 10220 N ELDORA AVE 91040

Application / Permit
23014-20000-00533
Plan Check / Job No.
B23VN01597
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
26'-7" X 9'-11" ADDITION TO & CONVERT (E) DETACHED REC ROOM INTO A (N) IRREGULAR SHAPED 26'-7" x 29'-2" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). - PER ENGINEER "COMPLY WITH DEPARTMENT ORDER effective date 11/14/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 6/27/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2023 APPLICANT
Assigned to Plan Check Engineer 2/15/2023 ARTIN ZARUKIAN
Building Plans Picked Up 2/22/2023 APPLICANT
Corrections Issued 2/27/2023 ARTIN ZARUKIAN
Applicant returned to address corrections 3/2/2023 LUKE GONZALES
Applicant returned to address corrections 3/3/2023 ALFRED RAMIREZ
Applicant returned to address corrections 6/16/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 6/20/2023 ISIS ARGUETA
Applicant returned to address corrections 6/22/2023 ALEC MOUSAKHANIAN
Issued 6/27/2023 APPLICANT
Permit Finaled 11/4/2024 DAVID JAMES
CofO Issued 11/4/2024 DAVID JAMES
Permit Finaled 11/4/2024 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 3/16/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 3/16/2023 FERNANDO GIL
Roof/Waste drainage to street Cleared 3/16/2023 FERNANDO GIL
Sewer availability Cleared 3/17/2023 FERNANDO GIL
Grading Pre-Inspection Cleared 3/21/2023 KIRK LINKLATER
Construction near power lines Cleared 6/13/2023 RIDWAN HARDY
GPI Written Notices Cleared 6/27/2023 ARTIN ZARUKIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Basso,, Alexandre; Lic. No.: C77670 7231 SUMMITROSE ST      TUJUNGA, CA 91042

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/3/2023 No Access for Inspection AGUSTIN ALVAREZMORALES
Insulation 8/10/2023 Partial Approval AGUSTIN ALVAREZMORALES
ELECTRICAL-Rough 10/11/2023 Corrections Issued AGUSTIN ALVAREZMORALES
Insulation 10/11/2023 Approved AGUSTIN ALVAREZMORALES
PLUMBING-Rough 10/11/2023 Approved AGUSTIN ALVAREZMORALES
Drywall Nailing 11/28/2023 Approved AGUSTIN ALVAREZMORALES
Green Building Rough 11/28/2023 Approved AGUSTIN ALVAREZMORALES
Interior/Exterior Lathing 11/28/2023 Approved AGUSTIN ALVAREZMORALES
BUILDING-Rough-Frame 2/20/2024 Not Ready for Inspection MARK VAN SLOOTEN
Final 2/20/2024 Not Ready for Inspection MARK VAN SLOOTEN
Footing/Foundation/Slab 2/20/2024 Not Ready for Inspection MARK VAN SLOOTEN
Green Building Final 2/20/2024 Not Ready for Inspection MARK VAN SLOOTEN
SGSOV-Seismic Gas S/O Valve 2/20/2024 SGSOV Not Ready MARK VAN SLOOTEN
Smoke Detectors 2/20/2024 Not Ready for Inspection MARK VAN SLOOTEN
BUILDING-Rough-Frame 2/21/2024 Approved MARK VAN SLOOTEN
Final 2/21/2024 Corrections Issued MARK VAN SLOOTEN
Footing/Foundation/Slab 2/21/2024 Approved MARK VAN SLOOTEN
Green Building Final 2/21/2024 Approved MARK VAN SLOOTEN
SGSOV-Seismic Gas S/O Valve 2/21/2024 SGSOV Not Ready MARK VAN SLOOTEN
Smoke Detectors 2/21/2024 Approved MARK VAN SLOOTEN
Final 8/13/2024 Conditional Approval MARK VAN SLOOTEN
SGSOV-Seismic Gas S/O Valve 8/13/2024 SGSOV No Gas MARK VAN SLOOTEN