6456-6458 N NAGLE AVE 91401
Certificate Information: 6456-6458 N NAGLE AVE 91401
- Application / Permit
- 23014-20000-00532
- Plan Check / Job No.
- B23VN01578
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. Convert (E) attached garage into an ADU and addition to ADU to build a 1000 sf ADU. PER LAMC LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 4/8/2024
- Issuing Office
- Current Status
- CofO Issued on 12/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | ALFREDO JARA |
| Corrections Issued | 5/8/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 10/17/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 10/22/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 3/23/2024 | ALFREDO JARA |
| Plan Check Approved | 4/7/2024 | ALFREDO JARA |
| Issued | 4/8/2024 | APPLICANT |
| CofO in Progress | 12/5/2024 | GAREN HAYRAPETYAN |
| Permit Finaled | 12/13/2024 | RUBEN SALAS |
| CofO Issued | 12/13/2024 | RUBEN SALAS |
| Permit Finaled | 12/13/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/13/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/14/2023 | DAGOVERTO GUERRERO |
| Low Impact Development (LID) | Cleared | 10/2/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/3/2023 | JOHN LIN |
Contact Information
| Contractor | A P W Builders Inc; Lic. No.: 643803-B | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/9/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/13/2024 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 5/14/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 5/15/2024 | Approved | OGANES TARAKHCHYAN |
| Sewer | 5/15/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2024 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 6/18/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/18/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 7/3/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/10/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/10/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/26/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/26/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 8/1/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 8/8/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 8/16/2024 | Approved | SALVADOR MARTINEZ |
| Shower Pan | 8/16/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 8/30/2024 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 10/11/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Service/Power Release | 11/25/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Final | 12/2/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 12/2/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2024 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Smoke Detectors | 12/2/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Final | 12/5/2024 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 12/5/2024 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 12/5/2024 | SGSOV Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 12/5/2024 | Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 12/5/2024 | Approved | GAREN HAYRAPETYAN |