5514 N MASON AVE 91367
Certificate Information: 5514 N MASON AVE 91367
- Application / Permit
- 23014-20000-00504
- Plan Check / Job No.
- B23VN01501
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SFD AND RELOCATE ATTACHED CARPORT. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 11/6/2023
- Issuing Office
- Current Status
- CofO Issued on 1/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2023 | GURUNATH NESARAJAH |
| Corrections Issued | 2/26/2023 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 10/12/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 10/16/2023 | CARLOS MONTES |
| Plan Check Approved | 11/5/2023 | CARLOS MONTES |
| Issued | 11/6/2023 | APPLICANT |
| CofO in Progress | 10/3/2024 | ALEXANDER HANDY |
| Permit Finaled | 1/31/2025 | JOHN JANSON |
| CofO Issued | 1/31/2025 | JOHN JANSON |
| Permit Finaled | 1/31/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 4/3/2023 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 6/27/2023 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 7/7/2023 | SERGIO VALENZUELA |
| Low Impact Development (LID) | Cleared | 9/12/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 9/23/2023 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 11/2/2023 | ROBERT PINA |
Contact Information
| Contractor | Trans-State Construction Inc; Lic. No.: 939104-B | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/8/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 11/8/2023 | Partial Approval | ALEXANDER HANDY |
| Pre-Inspection | 11/22/2023 | Approved | ALEXANDER HANDY |
| Wood Frame | 11/22/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2023 | Approved | ALEXANDER HANDY |
| Rough-Elec/Plmb/HVAC | 12/28/2023 | Corrections Issued | ALEXANDER HANDY |
| Shower Pan | 12/28/2023 | Approved | ALEXANDER HANDY |
| Wood Frame | 12/28/2023 | Partial Approval | ALEXANDER HANDY |
| Drywall Nailing | 1/4/2024 | Partial Approval | JEFFREY HARTLINE |
| Insulation | 1/4/2024 | Partial Approval | JEFFREY HARTLINE |
| Drywall Nailing | 1/22/2024 | No Access for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 2/27/2024 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 2/27/2024 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 2/27/2024 | Approved | ALEXANDER HANDY |
| Insulation | 2/27/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 2/27/2024 | Approved | ALEXANDER HANDY |
| Sewer | 3/21/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 8/21/2024 | Corrections Issued | ALEXANDER HANDY |
| Final | 8/21/2024 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 8/21/2024 | Approved | ALEXANDER HANDY |
| Green Building Final | 8/21/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| MERV13>=Final | 8/21/2024 | Approved | ALEXANDER HANDY |
| MERV13>=Rough | 8/21/2024 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 8/21/2024 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 8/21/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 10/2/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 10/2/2024 | Approved | ALEXANDER HANDY |
| Final | 10/2/2024 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 10/2/2024 | Approved | ALEXANDER HANDY |
| HVAC-Final | 10/2/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 10/2/2024 | Approved | ALEXANDER HANDY |