463-463 1/4 E 27TH ST 90011
Certificate Information: 463-463 1/4 E 27TH ST 90011
- Application / Permit
- 23014-20000-00483
- Plan Check / Job No.
- B23VN01444
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 22" X 10'-6" ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (e).
- Permit Issued
- Issued on 4/7/2023
- Issuing Office
- Current Status
- CofO Issued on 9/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 2/17/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 4/5/2023 | ALEC MOUSAKHANIAN |
| Issued | 4/7/2023 | APPLICANT |
| CofO in Progress | 7/16/2024 | ALEJANDRO DE ARTOLA |
| CofO in Progress | 8/5/2024 | DAVID FEILER |
| CofO in Progress | 8/24/2024 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 9/25/2024 | RUBEN SALAS |
| Permit Finaled | 9/25/2024 | RUBEN SALAS |
| CofO Issued | 9/25/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2023 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2023 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 2/28/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 2/28/2023 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/13/2023 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 9/6/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 9/6/2023 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 9/6/2023 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/12/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/30/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/6/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 12/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/11/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/15/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 12/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/19/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 12/19/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 12/28/2023 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 1/4/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/18/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 1/29/2024 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 2/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 2/9/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 2/9/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 2/9/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 2/26/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 2/27/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 3/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 3/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 3/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 3/12/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 3/12/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/1/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/8/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 4/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 4/8/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/8/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Final | 7/15/2024 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Special/Order Compliance | 7/17/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/23/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 9/20/2024 | Approved | ALEJANDRO DE ARTOLA |