14646 W BLEDSOE ST 91342
Certificate Information: 14646 W BLEDSOE ST 91342
- Application / Permit
- 23014-20000-00468
- Plan Check / Job No.
- B23VN01391
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 16'X25' BEDRM/BATH/CLOSET ADDN AT REAR TO EX 1-STORY SFD. ALL WORK PER WFPP.
- Permit Issued
- Issued on 6/7/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/14/2023 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 2/21/2023 | APPLICANT |
| Applicant returned to address corrections | 4/11/2023 | HAYATO TSUCHIYA |
| Plan Check Approved | 6/7/2023 | ALFRED RAMIREZ |
| Issued | 6/7/2023 | APPLICANT |
| CofO in Progress | 5/14/2024 | KEVIN BERBERYAN |
| CofO Issued | 10/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/12/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/6/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/10/2023 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 7/24/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 9/7/2023 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 9/7/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 9/22/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 9/22/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/22/2023 | Approved | MICHEL ABAJAN |
| Insulation | 10/6/2023 | Conditional Approval | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 10/6/2023 | Corrections Issued | KEVIN BERBERYAN |
| Drywall Nailing | 11/6/2023 | Approved | KEVIN BERBERYAN |
| Insulation | 11/6/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/6/2023 | Approved | KEVIN BERBERYAN |
| Sewer | 11/6/2023 | Approved | KEVIN BERBERYAN |
| Shower Pan | 11/6/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 4/17/2024 | Corrections Issued | KEVIN BERBERYAN |
| Final | 4/17/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 4/17/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Final | 4/17/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 4/17/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 4/17/2024 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 4/17/2024 | Corrections Issued | KEVIN BERBERYAN |
| Final | 5/13/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| Smoke Detectors | 5/13/2024 | Approved | KEVIN BERBERYAN |