8656 N FULLBRIGHT AVE 91306

Certificate Information: 8656 N FULLBRIGHT AVE 91306

Application / Permit
23014-20000-00455
Plan Check / Job No.
B23VN01345
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 19' X 20' DETACHED GARAGE WITH 18' X 21' ADDITION TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 3/19/2024
Issuing Office
Valley
Current Status
CofO in Progress on 5/27/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/3/2023 APPLICANT
Assigned to Plan Check Engineer 2/10/2023 ALEC MOUSAKHANIAN
Corrections Issued 2/13/2023 ALEC MOUSAKHANIAN
Building Plans Picked Up 2/14/2023 APPLICANT
Plan Check Approved 7/17/2023 MOHAMMAD ESMAILI
Issued 3/19/2024 APPLICANT
CofO in Progress 5/27/2026 JEFFREY HARTLINE

Permit Application Clearance Information

Address approval Cleared 2/16/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 2/16/2023 FERNANDO GIL
Roof/Waste drainage to street Cleared 2/16/2023 FERNANDO GIL
Sewer availability Cleared 2/17/2023 FERNANDO GIL
Construction near power lines Cleared 5/30/2023 RIDWAN HARDY
Construction within easement Cleared 5/30/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Chen,, Yeshen Jason; Lic. No.: C40169 20601 ALDA CT      WALNUT, CA 91789

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/9/2024 Approved JEFFREY HARTLINE
Excavation/Setback/Form/Re-Bar 4/23/2025 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 4/23/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 5/29/2025 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 5/29/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 9/17/2025 Approved JEFFREY HARTLINE
Green Building Rough 9/17/2025 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Rough 9/17/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 10/2/2025 Approved JEFFREY HARTLINE
Green Building Rough 10/2/2025 Approved JEFFREY HARTLINE
Shower Pan 10/2/2025 Approved JEFFREY HARTLINE
Insulation 10/20/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 10/20/2025 Approved JEFFREY HARTLINE
Drywall Nailing 11/3/2025 Approved JEFFREY HARTLINE
Insulation 11/3/2025 Approved JEFFREY HARTLINE
Final 5/1/2026 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 5/1/2026 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/1/2026 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 5/1/2026 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 5/26/2026 Approved JEFFREY HARTLINE
Final 5/26/2026 OK to Issue CofO JEFFREY HARTLINE
HVAC-Final 5/26/2026 Approved JEFFREY HARTLINE
PLUMBING-Final 5/26/2026 Approved JEFFREY HARTLINE