11933 W STRATHERN ST 91605

Certificate Information: 11933 W STRATHERN ST 91605

Application / Permit
23014-20000-00454
Plan Check / Job No.
B23VN01337
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 31'-6" X 47'-2" TO AND CONVERT EXISTING ACCESSORY DWELLING UNIT TO NEW SECOND UNIT PER SB9; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/30/2023
Issuing Office
Current Status
CofO Issued on 7/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2023 APPLICANT
Assigned to Plan Check Engineer 2/23/2023 SELLA BENYAMIN
Corrections Issued 2/28/2023 SELLA BENYAMIN
Quality Review Completed 3/8/2023 STEVEN KIM
Building Plans Picked Up 3/9/2023 APPLICANT
Applicant returned to address corrections 4/21/2023 SELLA BENYAMIN
Plan Check Approved 5/5/2023 SELLA BENYAMIN
Issued 5/30/2023 APPLICANT
CofO in Progress 7/1/2025 MATTHEW NELSON
Permit Finaled 7/31/2025 RUBEN SALAS
CofO Issued 7/31/2025 RUBEN SALAS
Permit Finaled 7/31/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 3/15/2023 TOMMY YIN
Senate Bill 9 Cleared 3/15/2023 ASHLEY RODARTE
Roof/Waste drainage to street Cleared 3/17/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 3/18/2023 COLIN LOREDO
Sewer availability Cleared 3/20/2023 COLIN LOREDO
Hydrant and Access approval Cleared 4/10/2023 KURT CORRAL
Miscellaneous Cleared 5/10/2023 NICHOLAS AYARS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/2/2023 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 10/3/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/13/2023 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 10/13/2023 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Not Ready for Inspection THOMAS FINNILA
Insulation 10/16/2023 Corrections Issued THOMAS FINNILA
Insulation 10/20/2023 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/6/2023 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 12/6/2023 Corrections Issued MATTHEW NELSON
HVAC-Rough 12/6/2023 Approved MATTHEW NELSON
PLUMBING-Rough 12/6/2023 Approved MATTHEW NELSON
Wood Frame 12/6/2023 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 12/18/2023 Partial Approval MATTHEW NELSON
Green Building Rough 12/18/2023 Approved MATTHEW NELSON
Insulation 1/5/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/5/2024 Corrections Issued MATTHEW NELSON
Drywall Nailing 1/22/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/22/2024 Approved MATTHEW NELSON
Shower Pan 1/22/2024 Approved MATTHEW NELSON
Underground Mechanical 1/22/2024 Not Ready for Inspection MATTHEW NELSON
Underground Mechanical 3/19/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/4/2025 Approved MATTHEW NELSON
Final 4/4/2025 Corrections Issued MATTHEW NELSON
Green Building Final 4/4/2025 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Approved MATTHEW NELSON
Smoke Detectors 4/4/2025 Approved MATTHEW NELSON
Final 6/30/2025 OK to Issue CofO MATTHEW NELSON
Green Building Final 6/30/2025 Approved MATTHEW NELSON