10541 N BAIRD AVE 91326
Certificate Information: 10541 N BAIRD AVE 91326
- Application / Permit
- 23014-20000-00451
- Plan Check / Job No.
- B23VN01331
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Addition of (N) caport to (E) SFD per engineered design ***SEE COMMENTS***
- Permit Issued
- Issued on 3/23/2023
- Issuing Office
- Current Status
- Issued on 3/23/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2023 | JASON JANGADA |
| Corrections Issued | 2/13/2023 | JASON JANGADA |
| Applicant returned to address corrections | 3/10/2023 | JASON JANGADA |
| Applicant returned to address corrections | 3/16/2023 | AMY GUEVARRA |
| Applicant returned to address corrections | 3/21/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 3/22/2023 | JOHNPAUL ISIP |
| Issued | 3/23/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2023 | JOSE DUARTE-DIAZ |
| Permit | Cleared | 2/27/2023 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 3/7/2023 | JOSE DUARTE-DIAZ |
| Stormwater Pollution Mitigatn | Cleared | 3/7/2023 | LUIS LUVANO |
| Public Works-Highway Ded. | Cleared | 3/7/2023 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 3/7/2023 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 3/7/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kyupelyan,, Emil; Lic. No.: C91238 | 8045 LASAINE AVE NORTHRIDGE, CA 91325 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/30/2023 | Corrections Issued | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 4/19/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 4/19/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 4/19/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 4/19/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 4/19/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Not Ready | DAVID SCANTLIN |
| Smoke Detectors | 4/19/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Wood Frame | 5/23/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Special/Order Compliance | 5/25/2023 | Approved | DAVID SCANTLIN |
| Pre-Inspection | 10/4/2023 | Corrections Issued | DAVID SCANTLIN |