6646-6648 N NEDDY AVE 91307

Certificate Information: 6646-6648 N NEDDY AVE 91307

Application / Permit
23014-20000-00443
Plan Check / Job No.
B23VN01297
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: Convert portion of (E) garage to living area for SFD (82sqft) Addtion to existing attached garage and converted to ADU (419sqft) per WFPP (Attached ADU per Ordinance,LAMC 12.22 A.33(c) and (e))
Permit Issued
Issued on 7/14/2023
Issuing Office
Current Status
CofO Issued on 11/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2023 APPLICANT
Assigned to Plan Check Engineer 2/17/2023 AUNG SOE
Corrections Issued 2/21/2023 AUNG SOE
Applicant returned to address corrections 4/28/2023 HANS SANTIAGO
Applicant returned to address corrections 5/11/2023 HANS SANTIAGO
Plan Check Approved 5/20/2023 KHUONG TRUONG
Issued 7/14/2023 APPLICANT
CofO in Progress 4/30/2024 TROY SANDERS
Permit Finaled 11/5/2024 JOHN JANSON
CofO Issued 11/5/2024 JOHN JANSON
Permit Finaled 11/5/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/15/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/15/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/19/2023 CARLOS AGUILERA
Sewer availability Cleared 4/19/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/31/2023 Partial Approval TROY SANDERS
Deputy Drilled-In Anchors 11/1/2023 Conditional Approval TROY SANDERS
Footing/Foundation/Slab 11/2/2023 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/21/2023 Partial Approval TROY SANDERS
ELECTRICAL-Rough 12/1/2023 Approved TROY SANDERS
Gas Test 12/1/2023 Approved TROY SANDERS
HVAC-Rough 12/1/2023 Approved TROY SANDERS
PLUMBING-Rough 12/1/2023 Approved TROY SANDERS
Insulation 1/3/2024 Approved TROY SANDERS
Service/Power Release 1/3/2024 Approved TROY SANDERS
Drywall Nailing 1/10/2024 Approved TROY SANDERS
BUILDING-Rough-Frame 4/29/2024 Approved TROY SANDERS
ELECTRICAL-Final 4/29/2024 Approved TROY SANDERS
Final 4/29/2024 OK to Issue CofO TROY SANDERS
Green Building Final 4/29/2024 Approved TROY SANDERS
Green Building Rough 4/29/2024 Approved TROY SANDERS
HVAC-Final 4/29/2024 Approved TROY SANDERS
PLUMBING-Final 4/29/2024 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 4/29/2024 SGSOV Approved TROY SANDERS
Smoke Detectors 4/29/2024 Approved TROY SANDERS