11081 N CARDAMINE DR 91042

Certificate Information: 11081 N CARDAMINE DR 91042

Application / Permit
23014-20000-00437
Plan Check / Job No.
B23VN01258
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: NEW ADDITION 10'3" X 5'3-1/2" TO THE EXISTING SFD FOR ENTRY FOYER AND BATHROOM , ADD 31'8-1/2" X 30'5"IRREGULAR SHAPED ADDITION TO (E) SFD TO REMODEL AND ENLARGE (3) BEDROOMS , ADD (3) BATHROOMS , RELOCATE BEDROOM , REMODEL TO (E) SFD TO CONVERT BEDROOM TO DINING ROOM , REMODEL KITCHEN , BATHROOM, REMODEL (3) BEDROOMS , ALL WORK PER ENGINEERING
Permit Issued
Issued on 7/24/2023
Issuing Office
Current Status
CofO Issued on 5/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 RARES BODEA
Corrections Issued 2/22/2023 RARES BODEA
Quality Review Completed 3/2/2023 STEVEN KIM
Applicant returned to address corrections 4/5/2023 RARES BODEA
Applicant returned to address corrections 7/18/2023 RARES BODEA
Plan Check Approved 7/20/2023 RARES BODEA
Issued 7/24/2023 APPLICANT
CofO in Progress 5/13/2024 WILLIAM WREN
Permit Finaled 5/17/2024 RUBEN SALAS
Permit Finaled 5/17/2024 RUBEN SALAS
CofO Issued 5/17/2024 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 6/27/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 7/12/2023 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 7/13/2023 COLIN LOREDO
Grading Pre-Inspection Cleared 7/20/2023 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 450 NORTH BRAND BLVD STE 600      GLENDALE, CA 91203

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/23/2023 Conditional Approval WILLIAM WREN
Footing/Foundation/Slab 8/25/2023 Approved WILLIAM WREN
PLUMBING-Rough 8/25/2023 Partial Approval WILLIAM WREN
Underground Mechanical 8/25/2023 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 9/12/2023 Partial Approval WILLIAM WREN
PLUMBING-Rough 9/12/2023 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 9/15/2023 Corrections Issued WILLIAM WREN
Insulation 9/15/2023 Partial Approval WILLIAM WREN
Deputy Wood Construction 9/18/2023 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 11/1/2023 Corrections Issued WILLIAM WREN
PLUMBING-Rough 11/1/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 11/7/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 11/7/2023 Approved WILLIAM WREN
HVAC-Rough 11/7/2023 Corrections Issued WILLIAM WREN
Wood Frame 11/7/2023 Corrections Issued WILLIAM WREN
Deputy Wood Construction 11/8/2023 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Approved WILLIAM WREN
Insulation 11/17/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 11/17/2023 Approved WILLIAM WREN
Drywall Nailing 12/4/2023 Approved WILLIAM WREN
Green Building Rough 12/4/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 12/4/2023 Approved WILLIAM WREN
Shower Pan 12/4/2023 Approved WILLIAM WREN
Final 4/5/2024 Corrections Issued KEVIN BERBERYAN
Gas Test 4/5/2024 Approved KEVIN BERBERYAN
Green Building Final 4/5/2024 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 4/5/2024 Approved KEVIN BERBERYAN
Final 4/12/2024 OK to Issue CofO WILLIAM WREN
Green Building Final 4/12/2024 Approved WILLIAM WREN