10235 N WHEATLAND AVE 91040

Certificate Information: 10235 N WHEATLAND AVE 91040

Application / Permit
23014-20000-00407
Plan Check / Job No.
B23VN01133
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 27'-8" X 16'-10" TO (E) SFD.
Permit Issued
Issued on 1/18/2024
Issuing Office
Valley
Current Status
CofO Issued on 10/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2023 APPLICANT
Assigned to Plan Check Engineer 2/10/2023 SERGIO MUNIZ
Corrections Issued 2/11/2023 SERGIO MUNIZ
Building Plans Picked Up 2/16/2023 APPLICANT
Applicant returned to address corrections 12/19/2023 JESSE ARELLANO
Issued 1/18/2024 APPLICANT
CofO in Progress 9/27/2024 DAVID ANDERSON
Permit Finaled 10/12/2024 DANIEL ORRANTE
CofO Issued 10/12/2024 DANIEL ORRANTE
Permit Finaled 10/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Tract Map conditions Cleared 4/7/2023 NATHAN ROMINE
Tract Map conditions Cleared 4/7/2023 NATHAN ROMINE
ZA Case Cleared 4/7/2023 NATHAN ROMINE
ZA Case Cleared 4/7/2023 NATHAN ROMINE
ZA Case Cleared 4/7/2023 NATHAN ROMINE
Grading Pre-Inspection Cleared 4/11/2023 MICHAEL TEMPLE
Roof/Waste drainage to street Cleared 4/11/2023 LEE GUILBEAUX
Hydrant and Access approval Cleared 4/28/2023 KURT CORRAL
Specific Plan Cleared 12/18/2023 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 12/26/2023 LEE GUILBEAUX
Sewer availability Cleared 12/26/2023 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 12/26/2023 LEE GUILBEAUX
Public Works-Sewers Cleared 12/26/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/13/2024 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 5/16/2024 Partial Approval DAVID ANDERSON
Deputy Steel/Welding 5/21/2024 Conditional Approval DAVID MATSON
Deputy Drilled-In Anchors 5/24/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 5/28/2024 Partial Approval DAVID ANDERSON
Footing/Foundation/Slab 5/28/2024 Partial Approval DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 6/6/2024 Approved DAVID ANDERSON
Footing/Foundation/Slab 6/6/2024 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 7/2/2024 Partial Approval DAVID ANDERSON
Green Building Rough 7/2/2024 Not Ready for Inspection DAVID ANDERSON
HVAC-Rough 7/2/2024 Corrections Issued DAVID ANDERSON
ELECTRICAL-Rough 7/15/2024 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Corrections Issued DAVID ANDERSON
Deputy Wood Construction 7/16/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 7/19/2024 Approved DAVID ANDERSON
Green Building Rough 7/19/2024 Approved DAVID ANDERSON
HVAC-Rough 7/19/2024 Approved DAVID ANDERSON
Insulation 7/30/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 7/30/2024 Approved DAVID ANDERSON
Drywall Nailing 8/16/2024 Approved DAVID ANDERSON
Final 9/26/2024 OK to Issue CofO DAVID ANDERSON
Green Building Final 9/26/2024 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 9/26/2024 SGSOV Approved DAVID ANDERSON
Smoke Detectors 9/26/2024 Approved DAVID ANDERSON