13717 W GAULT ST 91405
Certificate Information: 13717 W GAULT ST 91405
- Application / Permit
- 23014-20000-00406
- Plan Check / Job No.
- B23VN01128
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Addition and conversion of (E) detached storage/garage/carport into a detached ADU/carport per LAMC 12.22 A.33 (c) and (d)
- Permit Issued
- Issued on 5/2/2023
- Issuing Office
- Current Status
- CofO Issued on 4/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2023 | LUKE GONZALES |
| Corrections Issued | 2/9/2023 | LUKE GONZALES |
| Applicant returned to address corrections | 3/16/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 3/25/2023 | ZAW HAN |
| Plan Check Approved | 4/7/2023 | KHUONG TRUONG |
| Issued | 5/2/2023 | APPLICANT |
| Permit Closed-Status Void | 1/25/2024 | RYAN SALAZAR |
| Re-Activate Permit | 1/30/2024 | RYAN SALAZAR |
| CofO in Progress | 1/30/2024 | ROBERT GOLD |
| CofO Issued | 4/2/2024 | RUBEN SALAS |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2023 | MATTHEW MAHLEBASHIAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2023 | MATTHEW MAHLEBASHIAN |
| Roof/Waste drainage to street | Cleared | 3/9/2023 | MATTHEW MAHLEBASHIAN |
| Sewer availability | Cleared | 3/9/2023 | MATTHEW MAHLEBASHIAN |
| Construction within easement | Cleared | 4/5/2023 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/13/2023 | Partial Approval | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 6/15/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 6/22/2023 | Corrections Issued | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 8/22/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 8/24/2023 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2023 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 8/30/2023 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/26/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/26/2023 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 9/26/2023 | Approved | RYAN SALAZAR |
| Insulation | 10/3/2023 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 10/3/2023 | Partial Approval | ROBERT GOLD |
| Wood Frame | 10/6/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 10/16/2023 | Approved | RYAN SALAZAR |
| Sewer | 12/5/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/23/2024 | SGSOV Not Ready | RYAN SALAZAR |
| ELECTRICAL-Final | 1/25/2024 | Approved | RYAN SALAZAR |
| Final | 1/25/2024 | OK to Issue CofO | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/25/2024 | Approved | RYAN SALAZAR |
| Green Building Final | 1/25/2024 | Approved | RYAN SALAZAR |
| HVAC-Final | 1/25/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 1/25/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 1/25/2024 | Approved | RYAN SALAZAR |
| Service/Power Release | 2/14/2024 | Approved | RYAN SALAZAR |