7644 N WISH AVE 91406
Certificate Information: 7644 N WISH AVE 91406
- Application / Permit
- 23014-20000-00405
- Plan Check / Job No.
- B23VN01126
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-0" x 19'-8" DETACHED GARAGE AND (N) 21'-7" x 18'-4" ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 10/17/2025
- Issuing Office
- Current Status
- Issued on 10/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2023 | MADISON ODELL |
| Corrections Issued | 2/11/2023 | MADISON ODELL |
| Applicant returned to address corrections | 3/22/2023 | MADISON ODELL |
| Applicant returned to address corrections | 6/26/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 6/29/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 7/6/2023 | ALFRED RAMIREZ |
| Issued | 10/17/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/6/2023 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 4/6/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 4/17/2023 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 6/21/2023 | TINA MIRANDA |
| Construction within easement | Cleared | 6/21/2023 | TINA MIRANDA |
Contact Information
| Contractor | Kalbaklian Christopher; Lic. No.: 1106902-B | , |
| Engineer | Ni,, Zhang Yuan; Lic. No.: NA68149 | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/22/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Deputy Drilled-In Anchors | 10/29/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 11/3/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Special/Order Compliance | 11/3/2025 | Approved | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 11/5/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 11/6/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2025 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 11/21/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 11/26/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 11/26/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 11/26/2025 | Approved | GAREN HAYRAPETYAN |
| Gas Test | 12/2/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 12/2/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Sewer | 12/2/2025 | Approved | GAREN HAYRAPETYAN |
| Underground Mechanical | 12/2/2025 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 12/2/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 12/5/2025 | Not Ready for Inspection | CHRISTOPHER MORFIN |
| Insulation | 12/11/2025 | Approved | GAREN HAYRAPETYAN |
| Special/Order Compliance | 12/11/2025 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 12/19/2025 | Approved | CHRISTOPHER MORFIN |
| Special/Order Compliance | 1/7/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Drywall Nailing | 4/28/2026 | Approved | MICHAEL CORTEZ |