8751 N LOUISE AVE 91325

Certificate Information: 8751 N LOUISE AVE 91325

Application / Permit
23014-20000-00400
Plan Check / Job No.
B23VN01108
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 25'X32' STORAGE AND 6'X18' BREEZE WAY TO (E) SFD. COMPLY WITH DEPARTMENT ORDER effective date 05/20/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 4/13/2023
Issuing Office
Current Status
CofO Issued on 12/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2023 APPLICANT
Assigned to Plan Check Engineer 2/6/2023 JESSE ARELLANO
Corrections Issued 2/7/2023 JESSE ARELLANO
Building Plans Picked Up 2/10/2023 APPLICANT
Applicant returned to address corrections 3/29/2023 JESSE ARELLANO
Applicant returned to address corrections 4/11/2023 ALEC MOUSAKHANIAN
Issued 4/13/2023 APPLICANT
CofO in Progress 10/20/2023 MARK DOVICO
Permit Finaled 12/6/2023 DAVID JAMES
CofO Issued 12/6/2023 DAVID JAMES
Permit Finaled 12/6/2023 DAVID JAMES

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/22/2023 MEGAN GODINEZ
Stormwater Pollution Mitigatn Cleared 3/23/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/28/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/11/2023 Corrections Issued JOHN STEPHENS
Footing/Foundation/Slab 5/25/2023 No Access for Inspection JOHN STEPHENS
Pre-Inspection 5/30/2023 Approved MARK DOVICO
Deputy Drilled-In Anchors 8/7/2023 Approved MARIO CUEVAS
BUILDING-Rough-Frame 8/11/2023 Approved JOHN STEPHENS
ELECTRICAL-Rough 8/11/2023 Not Ready for Inspection JOHN STEPHENS
Green Building Rough 8/11/2023 Approved JOHN STEPHENS
Drywall Nailing 8/17/2023 Partial Approval JOHN STEPHENS
Floor/Roof Diaphrgm/Shear Wall 8/17/2023 Partial Approval JOHN STEPHENS
Green Building Final 8/17/2023 Not Ready for Inspection JOHN STEPHENS
Interior/Exterior Lathing 8/17/2023 Partial Approval JOHN STEPHENS
Wood Frame 8/17/2023 Partial Approval JOHN STEPHENS
ELECTRICAL-Rough 8/28/2023 Partial Approval JOHN STEPHENS
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Approved JOHN STEPHENS
Wood Frame 9/7/2023 Corrections Issued JOHN STEPHENS
Floor/Roof Diaphrgm/Shear Wall 9/11/2023 Approved JOHN STEPHENS
Wood Frame 9/11/2023 Approved JOHN STEPHENS
ELECTRICAL-Final 9/15/2023 Not Ready for Inspection JOHN STEPHENS
Final 9/15/2023 Corrections Issued JOHN STEPHENS
Green Building Final 9/15/2023 Not Ready for Inspection JOHN STEPHENS
SGSOV-Seismic Gas S/O Valve 9/15/2023 SGSOV Approved JOHN STEPHENS
Smoke Detectors 9/15/2023 Corrections Issued JOHN STEPHENS
Floor/Roof Diaphrgm/Shear Wall 9/20/2023 Approved JOHN STEPHENS
Wood Frame 9/20/2023 Approved JOHN STEPHENS
Drywall Nailing 9/26/2023 Partial Inspection JOHN STEPHENS
ELECTRICAL-Final 9/26/2023 Partial Inspection JOHN STEPHENS
Insulation 9/26/2023 Partial Inspection JOHN STEPHENS
Interior/Exterior Lathing 9/26/2023 Partial Inspection JOHN STEPHENS
Final 10/4/2023 Corrections Issued MARK DOVICO
Footing/Foundation/Slab 10/4/2023 Approved MARK DOVICO
Green Building Final 10/4/2023 Approved MARK DOVICO
PLUMBING-Final 10/4/2023 Approved MARK DOVICO
Smoke Detectors 10/4/2023 Approved MARK DOVICO
Final 10/10/2023 Corrections Issued MARK DOVICO
Final 10/16/2023 Conditional Approval MARK DOVICO