12801 W COLLINS ST 91607
Certificate Information: 12801 W COLLINS ST 91607
- Application / Permit
- 23014-20000-00395
- Plan Check / Job No.
- B23VN01077
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL OF (E) SINGLE FAMILY RESIDENCE AND 498.2 SF IRREGULAR SHAPED ADDITION TO THE REAR PORTION OF THE SFR. 1 OF 2. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/16/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2023 | JESSE ARELLANO |
| Corrections Issued | 2/7/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 2/13/2023 | APPLICANT |
| Applicant returned to address corrections | 6/2/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 7/26/2023 | OMAR GARNICA |
| Plan Check Approved | 9/25/2023 | OMAR GARNICA |
| Issued | 10/16/2023 | APPLICANT |
| CofO in Progress | 12/4/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 12/14/2024 | RUBEN SALAS |
| CofO Issued | 12/14/2024 | RUBEN SALAS |
| Permit Finaled | 12/14/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 7/27/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 7/31/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dermendjian,, Raffi Hrag; Lic. No.: C88261 | 9325 SHOSHONE AVENUE NORTHRIDGE, CA 91325 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/11/2024 | Partial Approval | CRAIG DAVIS |
| Deputy Drilled-In Anchors | 3/26/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 3/26/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 4/4/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 5/6/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 5/8/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 5/16/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 5/16/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Insulation | 5/20/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2024 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/5/2024 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2024 | Partial Approval | SALVADOR MARTINEZ |
| HVAC-Rough | 7/5/2024 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 7/5/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 7/22/2024 | Approved | JOSE AVILA |
| Shower Pan | 7/22/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 8/13/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/16/2024 | Partial Approval | SALVADOR MARTINEZ |
| Insulation | 8/20/2024 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 8/27/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Pre-Inspection | 9/5/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/7/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 11/7/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 11/7/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 11/7/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 11/7/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 11/7/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 11/7/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/13/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 11/13/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 11/13/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Final | 11/22/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Final | 12/2/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |