7005 N GEYSER AVE 91335

Certificate Information: 7005 N GEYSER AVE 91335

Application / Permit
23014-20000-00348
Plan Check / Job No.
B23VN00934
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 8'-0" x 19'-8" WITH 3'-0" x 19'-8" FRONT PORCH TO (E) S.F.D. PER ENGINEERING
Permit Issued
Issued on 2/6/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/26/2023 APPLICANT
Assigned to Plan Check Engineer 1/26/2023 LUISANGEL VALENZUELA
Corrections Issued 1/26/2023 LUISANGEL VALENZUELA
Issued 2/6/2023 APPLICANT
CofO in Progress 7/17/2023 SEAN WIRCH
Permit Finaled 7/28/2023 JOHN JANSON
CofO Issued 7/28/2023 JOHN JANSON
Permit Finaled 7/28/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/30/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 1/30/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/13/2023 Conditional Approval HORACE FULTZ
Excavation/Setback/Form/Re-Bar 4/24/2023 Approved JEFFREY BULL
Footing/Foundation/Slab 4/24/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 5/3/2023 Partial Approval JUSTIN HAWLEY
Pre-Inspection 5/3/2023 Approved JEFFREY BULL
ELECTRICAL-Rough 5/12/2023 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Approved JEFFREY BULL
Insulation 5/22/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 5/22/2023 Approved JEFFREY BULL
Drywall Nailing 5/24/2023 Approved JEFFREY BULL
Green Building Rough 5/24/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 7/14/2023 Approved JEFFREY BULL
ELECTRICAL-Final 7/14/2023 Approved JEFFREY BULL
Final 7/14/2023 OK to Issue CofO JEFFREY BULL
Green Building Final 7/14/2023 Approved JEFFREY BULL
HVAC-Final 7/14/2023 Approved JEFFREY BULL
PLUMBING-Final 7/14/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 7/14/2023 SGSOV Approved JEFFREY BULL
Smoke Detectors 7/14/2023 Approved JEFFREY BULL