10627-10629 N GOTHIC AVE 91344

Certificate Information: 10627-10629 N GOTHIC AVE 91344

Application / Permit
23014-20000-00323
Plan Check / Job No.
B23VN00834
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 21'2" X 21'2" GARAGE TO (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). (N) 7'8" X 11'1" ATTACHED LAUNDRY/ STORAGE ROOM. WORK DONE PER ENGINEERING.
Permit Issued
Issued on 8/29/2023
Issuing Office
Current Status
CofO Issued on 7/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2023 APPLICANT
Assigned to Plan Check Engineer 4/4/2023 MADISON ODELL
Corrections Issued 4/5/2023 MADISON ODELL
Applicant returned to address corrections 8/23/2023 MADISON ODELL
Plan Check Approved 8/27/2023 MADISON ODELL
Issued 8/29/2023 APPLICANT
CofO in Progress 7/18/2025 CHRISTOPHER ROJAS
Permit Finaled 7/25/2025 RUBEN SALAS
CofO Issued 7/25/2025 RUBEN SALAS
Permit Finaled 7/25/2025 RUBEN SALAS

Permit Application Clearance Information

ZA Case Cleared 4/11/2023 ASHLEY RODARTE
Address approval Cleared 4/13/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 4/13/2023 NIKKI ZULUETA
Sewer availability Cleared 4/13/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 4/18/2023 NIKKI ZULUETA
Construction near power lines Cleared 8/21/2023 TORI CHEN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: NA76761       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/26/2023 Partial Approval MICHEL ABAJAN
Sewer 10/26/2023 Approved MICHEL ABAJAN
Underground Mechanical 10/27/2023 Corrections Issued RAUL OLAGI
Underground Mechanical 10/31/2023 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 11/3/2023 Conditional Approval JAVIER RAMOS JR
Footing/Foundation/Slab 11/8/2023 Approved MICHEL ABAJAN
Deputy Drilled-In Anchors 11/22/2023 Conditional Approval ROBERT GOLD
Underground Mechanical 1/16/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 2/6/2024 Approved JOHN COLEMAN
HVAC-Rough 2/15/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 2/20/2024 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 2/26/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 2/26/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/4/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 3/18/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 3/18/2024 Conditional Approval KEVIN BERBERYAN
Drywall Nailing 4/2/2024 Approved KEVIN BERBERYAN
Shower Pan 5/14/2024 Corrections Issued MATTHEW NELSON
Shower Pan 5/20/2024 Corrections Issued LEONARD ROSS II
Shower Pan 5/29/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 2/7/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Final 5/13/2025 Corrections Issued JENNIFER RABUCHIN
Final 5/13/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 5/13/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/13/2025 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 5/13/2025 Approved JENNIFER RABUCHIN
Final 5/20/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 5/20/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Final 6/16/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Approved CHRISTOPHER ROJAS
Final 7/2/2025 Corrections Issued CHRISTOPHER ROJAS
Final 7/17/2025 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 7/17/2025 Approved CHRISTOPHER ROJAS