1643 S SPAULDING AVE 90019
Certificate Information: 1643 S SPAULDING AVE 90019
- Application / Permit
- 23014-20000-00313
- Plan Check / Job No.
- B23VN00786
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- ADDITION OF A 13'10" X 10'1" STORAGE ROOM TO THE (E) DETACHED GARAGE.
- Permit Issued
- Issued on 4/19/2023
- Issuing Office
- Current Status
- CofO Issued on 12/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2023 | SERGIO MUNIZ |
| Corrections Issued | 1/24/2023 | SERGIO MUNIZ |
| Issued | 4/19/2023 | APPLICANT |
| CofO in Progress | 12/1/2023 | ALIZAH MAYAGOITIA |
| CofO Issued | 12/5/2023 | DEROLD HAUFF |
| Permit Finaled | 12/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/1/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2023 | WALLIE JONG |
| Construction near power lines | Cleared | 3/31/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Built To Perfection Inc; Lic. No.: 837987-B | 22222 SHERMAN WAY #202 CANOGA PARK, CA 91303 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/28/2023 | Approved | LILIANA PORTILLO |
| METHANE-Barrier | 6/28/2023 | Approved | LILIANA PORTILLO |
| METHANE-Subgrade | 6/28/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/14/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/14/2023 | Approved | STUART CHAPMAN |
| Green Building Rough | 7/14/2023 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Rough | 7/14/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/25/2023 | Approved | MICHAEL LEWIS |
| Insulation | 8/8/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 8/21/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 10/23/2023 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 10/23/2023 | Approved | JUSTIN HAWLEY |
| Final | 10/23/2023 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 10/23/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Green Building Rough | 10/23/2023 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 10/23/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 10/23/2023 | SGSOV Approved | JUSTIN HAWLEY |
| Final | 11/27/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Green Building Final | 11/27/2023 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 11/27/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 12/1/2023 | OK to Issue CofO | ALIZAH MAYAGOITIA |