4141 N FARMDALE AVE 91604
Certificate Information: 4141 N FARMDALE AVE 91604
- Application / Permit
- 23014-20000-00242
- Plan Check / Job No.
- B23VN00582
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERT EX. DETACHED RECREATION ROOM INTO TWO-STORY ACCESSORY DWELLING UNIT WITH COVERED PATIO ENTRY AND BALCONY DECK ABOVE PER LAMC 12.22 A.33(c) AND (d). WORK PER ENGINEER. SPRIAL STAIRS PER LADBS STANDARD PLAN #111.
- Permit Issued
- Issued on 8/14/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 2/10/2023 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 2/15/2023 | APPLICANT |
| Plan Check Approved | 8/8/2023 | ROSENDO MEDINA |
| Issued | 8/14/2023 | APPLICANT |
| CofO in Progress | 11/14/2025 | JAVIER RAMOS JR |
| Permit Finaled | 12/19/2025 | RUBEN SALAS |
| CofO Issued | 12/19/2025 | RUBEN SALAS |
| Permit Finaled | 12/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 2/23/2023 | MIGUEL GAMBOA |
| Address approval | Cleared | 3/7/2023 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 3/7/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 3/16/2023 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 3/16/2023 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 3/16/2023 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 3/16/2023 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 8/3/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/3/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/6/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 11/6/2023 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 2/2/2024 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 2/2/2024 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 2/13/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 2/16/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 2/16/2024 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 2/16/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 3/13/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 3/13/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 3/13/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 3/13/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 3/26/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 3/29/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 4/11/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 4/19/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/25/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 6/25/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/3/2024 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 7/15/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/18/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/29/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/30/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 8/9/2024 | Corrections Issued | LOUIS ESCOTO |
| Interior/Exterior Lathing | 8/9/2024 | Approved | LOUIS ESCOTO |
| Insulation | 8/16/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 8/23/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 12/17/2024 | Approved | MICHAEL CORTEZ |
| Shower Pan | 12/17/2024 | Corrections Issued | MICHAEL CORTEZ |
| Shower Pan | 12/31/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/23/2025 | Approved | JAVIER RAMOS JR |
| Final | 10/23/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 10/23/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 10/23/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 10/23/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 10/23/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 10/23/2025 | Approved | JAVIER RAMOS JR |
| Final | 11/14/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 11/14/2025 | Approved | JAVIER RAMOS JR |