15838-15840 W CHATSWORTH ST 91344
Certificate Information: 15838-15840 W CHATSWORTH ST 91344
- Application / Permit
- 23014-20000-00241
- Plan Check / Job No.
- B23VN00581
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *eplan* Convert existing garage into a SB9 unit per Government Code Section 65852.21 and add new ADU on the 2nd floor of the SB9 unit per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33(c)-(d), (g).
- Permit Issued
- Issued on 9/17/2024
- Issuing Office
- Current Status
- CofO Issued on 2/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 2/16/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 3/15/2023 | QUAN NGHIEM |
| Plan Check Approved | 9/17/2024 | ARSALAN SHABESTARI |
| Plan Check Approved | 9/17/2024 | INTERNET PERMIT |
| Issued | 9/17/2024 | APPLICANT |
| CofO in Progress | 2/9/2026 | CHRISTOPHER ROJAS |
| Permit Finaled | 2/17/2026 | RUBEN SALAS |
| CofO Issued | 2/17/2026 | RUBEN SALAS |
| Permit Finaled | 2/17/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 4/14/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 4/17/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 7/8/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/8/2023 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 6/24/2024 | KURT CORRAL |
| Senate Bill 9 | Cleared | 7/24/2024 | DAVID URITA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/17/2024 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/17/2024 | Corrections Issued | MICHEL ABAJAN |
| Sewer | 10/17/2024 | Corrections Issued | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 12/4/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2025 | Partial Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 2/28/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 3/20/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 3/20/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/25/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 3/25/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 3/25/2025 | Approved | CHRISTOPHER ROJAS |
| Pre-Inspection | 3/25/2025 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 4/2/2025 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/18/2025 | Corrections Issued | KEVIN BERBERYAN |
| MERV13>=Rough | 6/18/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Wood Frame | 6/18/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/23/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2025 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Rough | 6/23/2025 | Approved | CHRISTOPHER ROJAS |
| Wood Frame | 6/23/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 7/31/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/5/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2025 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 9/11/2025 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/11/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Pre-Inspection | 9/11/2025 | Approved | CHRISTOPHER ROJAS |
| Sewer | 9/11/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 9/11/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 10/8/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/8/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Shower Pan | 10/8/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Insulation | 10/14/2025 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 10/14/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 10/14/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 10/20/2025 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Final | 1/7/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 1/7/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 1/7/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 1/7/2026 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Final | 1/7/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 1/7/2026 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/7/2026 | SGSOV Not Required | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/7/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 1/15/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Pre-Inspection | 1/15/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 1/21/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 2/5/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |