9139 N WHITE OAK AVE 91325
Certificate Information: 9139 N WHITE OAK AVE 91325
- Application / Permit
- 23014-20000-00208
- Plan Check / Job No.
- B23VN00499
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 29'-11" X 11'-10" PATIO COVER ADDITION TO (E) SINGLE FAMILY DWELLING - PER ENGERINEEING
- Permit Issued
- Issued on 2/28/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 1/21/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 1/24/2023 | APPLICANT |
| Plan Check Approved | 2/24/2023 | DANIEL ABRAMYAN |
| Issued | 2/28/2023 | APPLICANT |
| CofO in Progress | 7/3/2023 | JAVIER RAMOS JR |
| Permit Finaled | 7/18/2023 | MICHAEL SMITH |
| CofO Issued | 7/18/2023 | MICHAEL SMITH |
| Permit Finaled | 7/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/17/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/5/2023 | Partial Approval | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 5/8/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 5/11/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 5/11/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/22/2023 | Approved | JAVIER RAMOS JR |
| Final | 6/9/2023 | No Access for Inspection | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 6/9/2023 | SGSOV Not Ready | ROBERT GOLD |
| Smoke Detectors | 6/9/2023 | No Access for Inspection | ROBERT GOLD |
| Final | 6/16/2023 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 6/16/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 6/16/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 7/3/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| Smoke Detectors | 7/3/2023 | Approved | JAVIER RAMOS JR |