1520 N AVENUE 55 90042
Certificate Information: 1520 N AVENUE 55 90042
- Application / Permit
- 23014-20000-00207
- Plan Check / Job No.
- B23VN00492
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- 23'-4" X 19'-10" IRREGULAR SHAPED ADDITION TO EXISTING DETACHED GARAGE - ALL WORK PER WFPP
- Permit Issued
- Issued on 2/3/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2023 | APPLICANT |
| Application Withdrawn-Void | 1/17/2023 | FELIX FIGUEROA |
| Assigned to Plan Check Engineer | 1/19/2023 | ARTIN ZARUKIAN |
| Application Withdrawn | 1/19/2023 | ARTIN ZARUKIAN |
| Re-Activate Application | 1/23/2023 | FELIX FIGUEROA |
| Re-Activate Applicaton | 1/23/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 1/23/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 2/1/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 2/3/2023 | JEROME MAGAT PALMA |
| Issued | 2/3/2023 | APPLICANT |
| CofO in Progress | 8/4/2023 | CRAIG VAUGHAN |
| Permit Finaled | 8/7/2023 | RONALD MYRICK |
| CofO Issued | 8/7/2023 | RONALD MYRICK |
| Permit Finaled | 8/7/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/26/2023 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 1/30/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2023 | JEANIE LAM |
Contact Information
| Contractor | La Remodeling Co; Lic. No.: 932510-B | 6000 YORK BLVD STE A LOS ANGELES, CA 90042 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/15/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Drywall Nailing | 3/15/2023 | Approved | CRAIG VAUGHAN |
| Final | 3/15/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 3/15/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 3/15/2023 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 3/15/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 3/15/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 3/15/2023 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 3/21/2023 | Partial Approval | CRAIG VAUGHAN |
| Final | 3/21/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 3/21/2023 | Partial Approval | CRAIG VAUGHAN |
| Smoke Detectors | 3/21/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 3/23/2023 | Approved | CRAIG VAUGHAN |
| Final | 3/23/2023 | Partial Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 3/23/2023 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 3/23/2023 | Approved | CRAIG VAUGHAN |