1231 W 51ST ST 90037
Certificate Information: 1231 W 51ST ST 90037
- Application / Permit
- 23014-20000-00204
- Plan Check / Job No.
- B23VN00477
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 29'-8" X 20'-3" IRREGULAR SHAPED ADDITION AND REMODEL TO (E) SFD. WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 3/1/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 1/21/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 1/23/2023 | APPLICANT |
| Plan Check Approved | 3/1/2023 | MIROOSH KHACHATOORIAN |
| Issued | 3/1/2023 | APPLICANT |
| CofO in Progress | 2/9/2024 | RONNIE MINDANAO |
| CofO Issued | 2/22/2024 | DEROLD HAUFF |
| Permit Finaled | 2/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/3/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2023 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 2/23/2023 | TREVOR QUAN |
| ZI | Cleared | 2/27/2023 | RAFAEL FONTES |
Contact Information
| Contractor | Unlimited Construction & Remodeling Inc; Lic. No.: 1047565-B | 8500 WILSHIRE BLVD STE 829 BEVERLY HILLS, CA 90211 |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/10/2023 | Partial Inspection | SABAS ALONSO |
| Sewer | 5/10/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 5/17/2023 | Corrections Issued | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 5/19/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 5/19/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/14/2023 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 6/14/2023 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 6/14/2023 | Partial Approval | SABAS ALONSO |
| Insulation | 6/21/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 6/24/2023 | Partial Approval | JOSEPH MCGARRY |
| Wood Frame | 6/24/2023 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Not Ready for Inspection | SABAS ALONSO |
| Deputy Wood Construction | 6/28/2023 | Approved | DONALD CRICHLOW |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2023 | Partial Approval | SABAS ALONSO |
| Deputy Drilled-In Anchors | 7/17/2023 | Conditional Approval | BRENDAN MORELLI |
| Deputy Wood Construction | 8/1/2023 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 8/7/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/9/2023 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 8/9/2023 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 8/9/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/23/2023 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 8/23/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 8/23/2023 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/29/2023 | Approved | CHARLES BOGHOSKHAN |
| HVAC-Rough | 8/29/2023 | Approved | CHARLES BOGHOSKHAN |
| Insulation | 9/6/2023 | Approved | JOSH MEISTER |
| Drywall Nailing | 9/21/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/21/2023 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 9/27/2023 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 10/2/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Shower Pan | 10/2/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 10/4/2023 | Partial Approval | RONNIE MINDANAO |
| Shower Pan | 10/4/2023 | Approved | RONNIE MINDANAO |
| Final | 1/2/2024 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Final | 1/2/2024 | No Access for Inspection | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/2/2024 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 1/2/2024 | No Access for Inspection | HERBERT GIRON |
| Final | 1/5/2024 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 1/5/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 1/5/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 1/5/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 2/8/2024 | Approved | RONNIE MINDANAO |
| Final | 2/8/2024 | OK to Issue CofO | RONNIE MINDANAO |
| HVAC-Final | 2/8/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 2/8/2024 | Approved | RONNIE MINDANAO |