19863 W ROSCOE BLVD 91306
Certificate Information: 19863 W ROSCOE BLVD 91306
- Application / Permit
- 23014-20000-00187
- Plan Check / Job No.
- B23VN00458
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: ADDITION TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 3/6/2024
- Issuing Office
- Current Status
- CofO Issued on 4/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | DANIEL YIP |
| Corrections Issued | 2/23/2023 | DANIEL YIP |
| Quality Review Completed | 3/1/2023 | GARO TELMI |
| Applicant returned to address corrections | 9/21/2023 | DANIEL YIP |
| Applicant returned to address corrections | 10/20/2023 | DANIEL YIP |
| Applicant returned to address corrections | 11/14/2023 | DANIEL YIP |
| Applicant returned to address corrections | 12/18/2023 | DANIEL YIP |
| Plan Check Approved | 12/22/2023 | DANIEL YIP |
| Issued | 3/6/2024 | APPLICANT |
| CofO in Progress | 4/10/2025 | JEFFREY HARTLINE |
| Permit Finaled | 4/29/2025 | JOHN JANSON |
| CofO Issued | 4/29/2025 | JOHN JANSON |
| Permit Finaled | 4/29/2025 | JOHN JANSON |
Permit Application Clearance Information
| Stormwater Pollution Mitigatn | Cleared | 9/6/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 12/18/2023 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 12/18/2023 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2023 | CARLOS RAMIREZ |
Contact Information
| Contractor | Jas Development; Lic. No.: 1046957-B | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Service/Power Release | 1/22/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 4/9/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 4/9/2025 | Approved | JEFFREY HARTLINE |
| Final | 4/9/2025 | OK to Issue CofO | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 4/9/2025 | Approved | JEFFREY HARTLINE |
| Green Building Final | 4/9/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 4/9/2025 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 4/9/2025 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 4/9/2025 | Approved | JEFFREY HARTLINE |