2173 N REDCLIFF ST 90039

Certificate Information: 2173 N REDCLIFF ST 90039

Application / Permit
23014-20000-00158
Plan Check / Job No.
B23VN00360
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
18'7"X4'4" GARAGE ADDITION. "COMPLY WITH DEPARTMENT ORDER effective date 06/03/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 4/5/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 MARVEL DELACRUZ
Corrections Issued 2/24/2023 MARVEL DELACRUZ
Quality Review Completed 2/27/2023 OMID HEDAYAT
Building Plans Picked Up 2/28/2023 APPLICANT
Applicant returned to address corrections 2/21/2024 MARVEL DELACRUZ
Applicant returned to address corrections 3/13/2024 MARVEL DELACRUZ
Plan Check Approved 4/4/2024 MARVEL DELACRUZ
Plan Check Approved 4/4/2024 MARVEL DELACRUZ
Issued 4/5/2024 APPLICANT
CofO in Progress 10/2/2024 COREY HUPP
Permit Finaled 1/15/2025 DANIEL SANCHEZ
CofO Issued 1/15/2025 DANIEL SANCHEZ
Permit Finaled 1/15/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Miscellaneous Cleared 1/30/2024 RUBEN VASQUEZ
Miscellaneous Cleared 1/30/2024 RUBEN VASQUEZ
Roof/Waste drainage to street Cleared 2/2/2024 DAVID VO
Eng Process Fee Ord 176,300 Cleared 2/12/2024 WALLIE JONG
Grading Pre-Inspection Cleared 2/21/2024 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

RUBEN PEREZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT NILES, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
MARK BEVELAQUA, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL SANCHEZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
COREY HUPP, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
EMIL OPFFER, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/3/2024 Conditional Approval COREY HUPP
BUILDING-Rough-Frame 5/20/2024 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 5/20/2024 Not Ready for Inspection COREY HUPP
Green Building Rough 5/20/2024 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 6/7/2024 Not Ready for Inspection COREY HUPP
Footing/Foundation/Slab 6/7/2024 Corrections Issued COREY HUPP
Green Building Rough 6/7/2024 Approved COREY HUPP
BUILDING-Rough-Frame 6/27/2024 Not Ready for Inspection COREY HUPP
Footing/Foundation/Slab 6/27/2024 Approved COREY HUPP
BUILDING-Rough-Frame 9/17/2024 Approved COREY HUPP
Drywall Nailing 9/17/2024 Approved COREY HUPP
Final 9/17/2024 OK to Issue CofO COREY HUPP
Green Building Final 9/17/2024 Approved COREY HUPP
SGSOV-Seismic Gas S/O Valve 9/17/2024 SGSOV Not Required COREY HUPP
Smoke Detectors 9/17/2024 Approved COREY HUPP