5912 N CALVIN AVE 91356
Certificate Information: 5912 N CALVIN AVE 91356
- Application / Permit
- 23014-20000-00151
- Plan Check / Job No.
- B22VN19233
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- Eplan New Rec-room addition to the existing carport. NFPA-13D throughout.
- Permit Issued
- Issued on 3/1/2024
- Issuing Office
- Current Status
- CofO Issued on 11/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2023 | ZAW HAN |
| Corrections Issued | 1/11/2023 | ZAW HAN |
| Applicant returned to address corrections | 11/10/2023 | ZAW HAN |
| Applicant returned to address corrections | 12/7/2023 | MINA HABILI |
| Applicant returned to address corrections | 1/9/2024 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 1/25/2024 | ANDREW SANTIAGO |
| Issued | 3/1/2024 | APPLICANT |
| CofO in Progress | 9/18/2024 | JON MCHUGH |
| Permit Finaled | 11/19/2024 | JOHN JANSON |
| CofO Issued | 11/19/2024 | JOHN JANSON |
| Permit Finaled | 11/19/2024 | JOHN JANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 2/2/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2023 | CARLOS AGUILERA |
| Tenant Habitability Plan | Cleared | 2/16/2023 | ISMAEL HERNANDEZ |
| Hydrant and Access approval | Cleared | 6/29/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 8/25/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 9/26/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/21/2024 | Partial Approval | JON MCHUGH |
| Deputy Drilled-In Anchors | 3/26/2024 | Partial Approval | SEAN WIRCH |
| Excavation/Setback/Form/Re-Bar | 3/29/2024 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2024 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 5/15/2024 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Rough | 5/22/2024 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 5/22/2024 | Approved | MORRIS JACKSON |
| ELECTRICAL-Rough | 5/28/2024 | Partial Approval | JON MCHUGH |
| Verify Sprinkler Sign Off | 5/28/2024 | Approved | JON MCHUGH |
| Insulation | 6/10/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 6/12/2024 | Approved | ALEXANDER HANDY |
| Sewer | 7/3/2024 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 8/17/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 8/17/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/17/2024 | Approved | MISAEL ESPARZA |
| Green Building Final | 8/17/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 8/17/2024 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/17/2024 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 8/17/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/18/2024 | Off-Hour Fees Due | |
| Final | 8/18/2024 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 8/18/2024 | Off-Hour Fees Due | |
| Green Building Final | 8/18/2024 | Off-Hour Fees Due | |
| Green Building Rough | 8/18/2024 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 8/18/2024 | Off-Hour Fees Due | |
| Smoke Detectors | 8/18/2024 | Off-Hour Fees Due | |
| BUILDING-Rough-Frame | 9/13/2024 | Approved | JON MCHUGH |
| Final | 9/13/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 9/13/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 9/13/2024 | SGSOV Not Ready | JON MCHUGH |
| ELECTRICAL-Final | 9/17/2024 | Approved | JON MCHUGH |
| Final | 9/17/2024 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 9/17/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 9/17/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 9/17/2024 | SGSOV Approved | JON MCHUGH |