465 N CROFT AVE 90048

Certificate Information: 465 N CROFT AVE 90048

Application / Permit
23014-20000-00129
Plan Check / Job No.
B23VN00224
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRREGULAR SHAPED 8'-7" x 19'-9"ADDITION TO ENLARGE (E) LIVING ROOM, KITCHEN, ADD POWDER ROOM. ALL WORK PER ENGR DESIGN.
Permit Issued
Issued on 1/27/2023
Issuing Office
Current Status
CofO Issued on 2/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2023 APPLICANT
Assigned to Plan Check Engineer 1/11/2023 JESSE ARELLANO
Corrections Issued 1/12/2023 JESSE ARELLANO
Building Plans Picked Up 1/13/2023 APPLICANT
Applicant returned to address corrections 1/25/2023 HAYATO TSUCHIYA
Issued 1/27/2023 APPLICANT
CofO in Progress 2/17/2026 JOSH MEISTER
No Progress 2/23/2026 JOSH MEISTER
CofO in Progress 2/23/2026 JOSH MEISTER
CofO Issued 2/26/2026 DEROLD HAUFF
Permit Finaled 2/26/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/18/2023 CINDY QI
Roof/Waste drainage to street Cleared 1/18/2023 CINDY QI

Contact Information

Contractor One Creative Group Inc; Lic. No.: 628294-B 1276 N SWEETZER AVE #6      WEST HOLLYWOOD, CA 90069
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/1/2023 Conditional Approval MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 2/2/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 2/2/2023 Partial Approval MICHAEL LEWIS
Deputy Reinf. Concrete 2/3/2023 Conditional Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 3/3/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 3/17/2023 Approved MICHAEL LEWIS
HVAC-Rough 3/17/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 3/17/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 3/20/2023 Partial Approval MICHAEL LEWIS
Green Building Rough 3/20/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 3/20/2023 Approved MICHAEL LEWIS
METHANE-Rough 3/20/2023 Approved MICHAEL LEWIS
Insulation 3/22/2023 Approved ALIZAH MAYAGOITIA
Drywall Nailing 3/24/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 7/3/2025 Approved JOSE MACIAS
Final 7/3/2025 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 7/3/2025 Approved JOSE MACIAS
Green Building Final 7/3/2025 Not Ready for Inspection JOSE MACIAS
METHANE-Barrier 7/3/2025 Approved JOSE MACIAS
METHANE-Subgrade 7/3/2025 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 7/3/2025 SGSOV Approved JOSE MACIAS
Smoke Detectors 7/3/2025 Approved JOSE MACIAS
Final 2/13/2026 OK to Issue CofO JOSH MEISTER
Green Building Final 2/13/2026 Approved JOSH MEISTER