15096 W NURMI ST 91342
Certificate Information: 15096 W NURMI ST 91342
- Application / Permit
- 23014-20000-00128
- Plan Check / Job No.
- B23VN00219
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 21'x 25' DETACHED GARAGE WITH 27'-0" x 30'-0" IRREG.SHAPED ADDITION TO NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 11/30/2023
- Issuing Office
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 1/14/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 11/17/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 11/24/2023 | MIROOSH KHACHATOORIAN |
| Issued | 11/30/2023 | APPLICANT |
| CofO in Progress | 6/26/2024 | KEVIN BERBERYAN |
| CofO Issued | 8/5/2024 | RUBEN SALAS |
| Permit Finaled | 8/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/15/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 3/15/2023 | FERNANDO GIL |
| Low Impact Development | Cleared | 11/2/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 11/13/2023 | CARLOS RAMIREZ |
| Grading Pre-Inspection | Cleared | 11/19/2023 | MIROOSH KHACHATOORIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: NA53080 | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/1/2023 | Conditional Approval | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 12/4/2023 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 12/7/2023 | Partial Approval | KEVIN BERBERYAN |
| Sewer | 12/7/2023 | Approved | KEVIN BERBERYAN |
| Wood Frame | 12/7/2023 | Partial Approval | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2023 | Conditional Approval | ROBERT GOLD |
| PLUMBING-Rough | 12/19/2023 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 12/19/2023 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2023 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 12/27/2023 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 1/2/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 1/16/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/30/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 1/30/2024 | Approved | MICHEL ABAJAN |
| Wood Frame | 1/30/2024 | Approved | MICHEL ABAJAN |
| Insulation | 2/6/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/12/2024 | Corrections Issued | THOMAS FINNILA |
| Drywall Nailing | 2/12/2024 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/15/2024 | Conditional Approval | THOMAS FINNILA |
| Drywall Nailing | 2/15/2024 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 4/1/2024 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Final | 4/1/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 4/10/2024 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 4/10/2024 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 4/10/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Final | 5/14/2024 | Approved | KEVIN BERBERYAN |
| Final | 6/12/2024 | Partial Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/25/2024 | Approved | KEVIN BERBERYAN |
| Final | 6/25/2024 | OK to Issue CofO | KEVIN BERBERYAN |