17167 W MIDWOOD DR 91344
Certificate Information: 17167 W MIDWOOD DR 91344
- Application / Permit
- 23014-20000-00120
- Plan Check / Job No.
- B23VN00194
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF (N) 14'-0" x 36'-0" ATTACHED PATIO COVER TO (E) S.F.D. PER INFORMATION BULLETIN P/BC 2020-006
- Permit Issued
- Issued on 1/12/2023
- Issuing Office
- Current Status
- CofO Issued on 6/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2023 | ALFRED RAMIREZ |
| Corrections Issued | 1/9/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 1/12/2023 | ISIS ARGUETA |
| Issued | 1/12/2023 | APPLICANT |
| CofO in Progress | 6/5/2023 | STEVEN BACK |
| CofO Issued | 6/6/2023 | JOHN JANSON |
| Permit Finaled | 6/6/2023 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/9/2023 | ALFRED RAMIREZ |
| Roof/Waste drainage to street | Cleared | 1/9/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2023 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 1/11/2023 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 1/11/2023 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 1/11/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/11/2023 | Partial Approval | SEAN HAUPT |
| Special/Order Compliance | 4/11/2023 | Corrections Issued | SEAN HAUPT |
| Wood Frame | 4/11/2023 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 4/19/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 4/19/2023 | Approved | SEAN HAUPT |
| Pre-Inspection | 4/19/2023 | Partial Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 5/10/2023 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 5/12/2023 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 6/5/2023 | Approved | STEVEN BACK |
| Final | 6/5/2023 | OK to Issue CofO | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 6/5/2023 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 6/5/2023 | Approved | STEVEN BACK |