18948 W DELANO ST 91335

Certificate Information: 18948 W DELANO ST 91335

Application / Permit
23014-20000-00112
Plan Check / Job No.
B23VN00170
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan 496 s.f. to an existing house expand the existing bedroom and add a new bathroom
Permit Issued
Issued on 4/21/2023
Issuing Office
Current Status
CofO Issued on 7/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2023 APPLICANT
Assigned to Plan Check Engineer 1/13/2023 JOHNPAUL ISIP
Corrections Issued 1/16/2023 JOHNPAUL ISIP
Applicant returned to address corrections 1/25/2023 KHUONG TRUONG
Applicant returned to address corrections 4/4/2023 JOHNPAUL ISIP
Applicant returned to address corrections 4/7/2023 JOHNPAUL ISIP
Plan Check Approved 4/13/2023 JOHNPAUL ISIP
Issued 4/21/2023 APPLICANT
CofO in Progress 5/29/2024 JON MCHUGH
Permit Finaled 7/9/2024 JOHN JANSON
CofO Issued 7/9/2024 JOHN JANSON
Permit Finaled 7/9/2024 JOHN JANSON

Permit Application Clearance Information

ZI Cleared 2/8/2023 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 2/9/2023 JOSE DUARTE-DIAZ
Low Impact Development Cleared 3/28/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 4/1/2023 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/26/2023 Conditional Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 4/28/2023 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 5/3/2023 Approved JON MCHUGH
BUILDING-Rough-Frame 5/12/2023 Corrections Issued JON MCHUGH
Insulation 5/17/2023 Partial Approval JON MCHUGH
Wood Frame 5/17/2023 Partial Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Partial Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 6/12/2023 Approved JON MCHUGH
PLUMBING-Rough 6/12/2023 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 6/23/2023 Corrections Issued JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 6/23/2023 Partial Approval JON MCHUGH
PLUMBING-Rough 6/23/2023 Not Ready for Inspection JON MCHUGH
BUILDING-Rough-Frame 7/5/2023 Approved JON MCHUGH
ELECTRICAL-Rough 7/5/2023 Approved JON MCHUGH
HVAC-Rough 7/5/2023 Approved JON MCHUGH
Interior/Exterior Lathing 7/5/2023 Partial Approval JON MCHUGH
PLUMBING-Rough 7/5/2023 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 7/10/2023 Approved JON MCHUGH
Insulation 7/10/2023 Approved JON MCHUGH
PLUMBING-Rough 7/10/2023 Approved JON MCHUGH
Drywall Nailing 7/14/2023 Approved JOHN KIDWELL
Final 10/23/2023 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 10/23/2023 SGSOV Not Ready JON MCHUGH
Smoke Detectors 10/23/2023 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Final 5/28/2024 Approved JON MCHUGH
Final 5/28/2024 OK to Issue CofO JON MCHUGH
HVAC-Final 5/28/2024 Approved JON MCHUGH
PLUMBING-Final 5/28/2024 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 5/28/2024 SGSOV Approved JON MCHUGH
Smoke Detectors 5/28/2024 Approved JON MCHUGH