19654 W PARTHENIA ST 91324
Certificate Information: 19654 W PARTHENIA ST 91324
- Application / Permit
- 23014-20000-00110
- Plan Check / Job No.
- B23VN00169
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- ePLAN. NEW DETACHED GARAGE WITH A 2ND FLOOR RECREATION ROOM.
- Permit Issued
- Issued on 7/7/2023
- Issuing Office
- Current Status
- CofO Issued on 6/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | KEVIN MORALES |
| Corrections Issued | 2/21/2023 | KEVIN MORALES |
| Quality Review Completed | 2/21/2023 | EUGENE BARBEAU |
| Plan Check Approved | 4/20/2023 | KEVIN MORALES |
| Issued | 7/7/2023 | APPLICANT |
| CofO in Progress | 6/4/2024 | CHRIS CHRISTENSEN |
| Permit Finaled | 6/14/2024 | JOHN JANSON |
| CofO Issued | 6/14/2024 | JOHN JANSON |
| Permit Finaled | 6/14/2024 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/6/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 4/6/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2023 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 4/11/2023 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 4/11/2023 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 4/11/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/15/2024 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 2/15/2024 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 2/15/2024 | Approved | JEFFREY HARTLINE |
| Deputy Reinf. Concrete | 2/16/2024 | Conditional Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 3/11/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 3/11/2024 | Corrections Issued | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 3/11/2024 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 3/11/2024 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 3/21/2024 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Corrections Issued | MORRIS JACKSON |
| Interior/Exterior Lathing | 3/29/2024 | Partial Approval | JEFFREY HARTLINE |
| HVAC-Rough | 4/5/2024 | Approved | JEFFREY HARTLINE |
| Insulation | 4/5/2024 | Approved | JEFFREY HARTLINE |
| Insulation | 4/8/2024 | Partial Inspection | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 4/8/2024 | Partial Inspection | KRISTEN CAUSEY |
| Drywall Nailing | 4/15/2024 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 4/15/2024 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 5/20/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 5/20/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 5/20/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/20/2024 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Service/Power Release | 5/20/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 5/20/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 5/28/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 5/28/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/28/2024 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 5/28/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 6/3/2024 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 6/3/2024 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 6/3/2024 | Approved | CHRIS CHRISTENSEN |