13275 W JUDD ST 91331
Certificate Information: 13275 W JUDD ST 91331
- Application / Permit
- 23014-20000-00099
- Plan Check / Job No.
- B23VN00161
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- IRREG SHAPED 37'-3" X 20' ADDITION AND 20'-5" X 7'-4" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 11/22/2023
- Issuing Office
- Current Status
- CofO Issued on 2/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 1/28/2023 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 7/18/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 7/19/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 7/24/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 7/26/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 11/19/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 11/21/2023 | ALEC MOUSAKHANIAN |
| Issued | 11/22/2023 | APPLICANT |
| CofO in Progress | 1/29/2025 | MICHEL ABAJAN |
| Permit Finaled | 2/5/2025 | RUBEN SALAS |
| CofO Issued | 2/5/2025 | RUBEN SALAS |
| Permit Finaled | 2/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2023 | RYAN KIM |
| Sewer availability | Cleared | 2/3/2023 | RYAN KIM |
| Miscellaneous | Cleared | 2/6/2023 | NELSON RODRIGUEZ |
| Roof/Waste drainage to street | Cleared | 7/12/2023 | RYAN KIM |
| Stormwater Pollution Mitigatn | Cleared | 7/12/2023 | ERNEST TSE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/9/2024 | No Access for Inspection | MICHEL ABAJAN |
| Pre-Inspection | 2/12/2024 | Corrections Issued | MICHEL ABAJAN |
| Pre-Inspection | 4/17/2024 | Corrections Issued | JOHN COLEMAN |
| Pre-Inspection | 4/17/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 5/1/2024 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/1/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2024 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/30/2024 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Rough | 5/30/2024 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 5/30/2024 | Corrections Issued | KEVIN BERBERYAN |
| Sewer | 5/30/2024 | Approved | KEVIN BERBERYAN |
| Wood Frame | 5/30/2024 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 6/3/2024 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 6/3/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/3/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/7/2024 | Approved | MICHEL ABAJAN |
| Wood Frame | 6/7/2024 | Approved | MICHEL ABAJAN |
| Insulation | 6/10/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/13/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/28/2024 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 6/28/2024 | Approved | MICHEL ABAJAN |
| Pre-Inspection | 7/1/2024 | Partial Inspection | MICHEL ABAJAN |
| Green Building Final | 8/19/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/19/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/1/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 10/1/2024 | Approved | MICHEL ABAJAN |
| Final | 10/1/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 10/1/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 10/1/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 10/1/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 10/1/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 10/1/2024 | Approved | MICHEL ABAJAN |
| Final | 10/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 10/18/2024 | Partial Approval | JENNIFER RABUCHIN |
| Service/Power Release | 10/18/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 1/28/2025 | OK to Issue CofO | MICHEL ABAJAN |